Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: PLUMBING - ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 07/16/2019 |
PLUMBING - ABOVE CEILING |
|
Approved |
|
| 06/14/2019 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Computer room. |
| 06/13/2019 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Yoga room Is ready for sheet rock. Computer room second layer of sheet rock, however missing fire caulk. |
| 06/12/2019 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
MEP’s only for lobby, missing two hour firewall between lobby and fitness Center. The yoga room is not complete |
| 02/07/2019 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
First level of North town house drain waste and vent OK. |
| 02/05/2019 |
PLUMBING - ABOVE CEILING |
|
Cancelled |
canceled by contractor |
| 02/01/2019 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Plumbing above ceiling first floor gridlines 1 to 4 from A to E .8 and from E to J / 5 to 7 |
| 01/30/2019 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Above first floor sections row A through E and line 5 thru 7 |