Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 07/16/2019 |
PLUMBING - ROUGH, SOIL |
|
Approved |
See foundation permit T18CM 00899. |
| 07/10/2019 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
I will need to meet with the contractor to ensure all work is complete. |
| 12/06/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Waste from NE corner W to midway ok to cover |
| 12/04/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
6 inch trunk north side of building and I’ll connecting pipes in basement |
| 11/30/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Level #1, 2each 4" waste lines at GL: F-G/5.3, approximately 40'. Ok to cover progress areas |
| 11/28/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
All waistlines for the east side planters are OK to cover. |
| 11/27/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
All underground plumbing for three town houses east side of building OK to cover. |