Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 07/16/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
See foundation permit T18CM 00899 |
| 07/10/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
I will need to meet with the contractor to ensure all work is complete. |
| 12/03/2018 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Footing at southeast corner south of ramp OK to pour after loose dirt is cleaned away from steal. |
| 11/20/2018 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Wall north side of parking ramp (GL6) adjust spacing of vertical rebar’s then OK to pour. |
| 11/15/2018 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Level #1 stem wall footings at GL: F.3/1.5 - 3.2; F.3 - J/1.5; 1.5 - 3/J. OK to place concrete. |
| 11/07/2018 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Both elevator shaft and stairway OK to poor level five. |