Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T16CM09380
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/23/2019 | EXCAVATION/LAYOUT REBAR & ZON | Approved | Refer to permit T17CM00004. | |
10/31/2017 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | ||
10/27/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SHOTCRETE SHORING IS COMPLETE! FOOTING FOR TOWER CRANE WILL BE READY TO POUR 10/28/17 7:00 AM. PROVIDE SPECIAL INSPECTION REPORTS. | |
10/26/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SHOTCRETE ONGOING | |
10/25/2017 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | ||
10/24/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | RAMP RELOCATED TO NW CORNER. NORTH WALL FROM 11 TO 18 READY FOR SHOTCRETE TO SECOND LEVEL. EAST SIDE FROM 19 TO 24 OK TO SHOTCRETE TO THIRD LEVEL | |
10/13/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | INFORMATION ONLY. WILL RESCHEDULE FOR 16 OCTOBER. | |
10/12/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | on going soils nail on west side. | |
10/11/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BOTTOM OF SITE WEST SIDE, AND WEST 1/2 OF NORTH AND SOUTH. NAILING AND EXCAVATION ONGOING ON EAST SIDE. | |
10/09/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LOADING OF SOIL NAILS AND EXCAVATION CONTINUING | |
10/05/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | progress on soils nails on going, equipment failure on this date. | |
10/04/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | progress on soils nails on going. | |
10/03/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | progress on soils nails | |
10/02/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
09/29/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | On going soils nails on south side. | |
09/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SOIL NAILS AT SOUTH EASTCORNER AT TRANSFORMER. | |
09/27/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | STARTING PROOF TEST ON EAST SIDE. SECOND COURSE OF SHOTCRETE ON WEST SIDE, FINAL SOIL NAILS ON NORTH AND NORTHWEST AREAS. | |
09/26/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LOAD PROOFING WEST SIDE CONTINUES. SOIL NAILING SOUTHEAST CORNER STARTING, SHOTCRETE PREP ON SOUTHWEST AREA ONGOING. | |
09/25/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LOAD PROOFING WEST SIDE ONGOING | |
09/22/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SOIL NAILING ON NORTH SIDE IS ONGOING. NAIL PROOFING IS ONGOING ON WEST SIDE. SHOTCRETE AT SOUTHWEST CORNER IS DONE. |
|
09/20/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SOUTHWEST CORNER READY FOR SHOTCRETE, WEST SIDE READY FOR LOAD TESTING. | |
09/19/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PREPARING FOR PROOF TESTING OF SOIL NAILS ON WEST SIDE OF SITE. PREPARING TO PLACE SOIL NAILS AT SOUTHEAST CORNER OF PROPERTY. | |
09/18/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SOIL NAILING AND SHOTCRETE CONTINUING. | |
09/13/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SETTING UP FOR PROOF TESTING WEST SIDE. EXCAVATING NORTH SIDE FOR SECOND LIFT OF SHOTCRETE. | |
09/12/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SOIL NAILING AND SHOTCRETE CONTINUE ON WEST AND NORTH SIDE. | |
09/11/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SHOTCRETE ON NORTH END ONGOING. SOIL NAILS STOPPED, PUMP IS DEAD. | |
09/08/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SOIL NAILING ONGOING ON EAST SIDE OF SITE. | |
09/07/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SHOT-CREAT ON EAST AND NORTH END OK TO SHOOT | |
09/05/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SOIL NAILING COMPLETE ON WEST SIDE UPPER ROW. | |
09/01/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SOIL NAILING ON WEST SIDE IS ONGOING. | |
08/30/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 4 SOILS NAILS ON WEST SIDE NORTH TO SOUTH | |
08/22/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | WEST SIDE READY FOR SOIL NAILS AND GUNITE. | |
08/15/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | WEST SIDE OF PROPERTY PILES 1 AND 89 READY TO SET BEAM AND SLURRY | |
08/11/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | soldier piles #5, #7, #10, #11, and #12 ok | |
08/01/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SOLDIER PILES ON WEST SIDE OF PROPERTY ARE INSTALLED EXCEPT #79 AND #89. CONFIRMATION OF LOCATION FOR #89 AND #1 IS PENDING. SOUTHERN AREA OF TIGHTER SPACING IS OFF PLAN BY 2'. WILL REQUIRE APPROVAL BY EOR. |