Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 08/03/2010 |
ENGINEERING - FINAL |
|
Approved |
Ramp replaced and in conformance. Approved |
| 07/08/2010 |
ENGINEERING - FINAL |
|
Denied |
Corrections to new curb ramp have not been completed, received a letter from Raytheon Facilities Manager addressing the existing ramps. |
| 05/24/2010 |
ENGINEERING - FINAL |
|
Denied |
access ramp in 3 areas not per code, slope to steep max slope of 12:1 required, remove and replace. |