Inspection History: PLUMBING - GAS PRESS TEST FNL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/24/2010 | PLUMBING - GAS PRESS TEST FNL | Approved | IVRS - Inspection :* | |
| 03/22/2010 | PLUMBING - GAS PRESS TEST FNL | Not ready for Inspection | IVRS - Inspection :* PROVIDE FULL SIZE DRAIN PIPING FROM FCF -- COMPLETE BUSTER AT VENT FOR REL--- |
|
| 03/10/2010 | PLUMBING - GAS PRESS TEST FNL | Not ready for Inspection | IVRS - Inspection :* | |
| 10/22/2009 | PLUMBING - GAS PRESS TEST FNL | Partial Approval | IVRS - Inspection :* 1) COMPLETE ALL GAS PIPING 2) SOAP TEST LATER, FITTING TO BE INSTALLED 3) PROVIDE BACKFLOW CERT 4) INSTALL MAKE UP WATER PER APPROVED PLAN |