Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/19/2009 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* 1) 60 PSI ON LAST 60' OF GAS PIPING OK 2) PROVIDE RED LINE DRAWINGS FOR ALL CHANGES |
|
| 09/15/2009 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* 1) NO PLUMBING IN PHASE 1 |
|
| 07/14/2009 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* 1) SUPPORT TO BE INSTALLED FOR ALL GAS PIPING 2) PROVIDE GAS PIPING SPECS FOR VALVES AND PIPING 3) THREADED GAS PIPING 60 PSI TEST 2" FROM STUB DOWN INTO FIRST FLOOR MECHANICAL ROOM AND FROM ROOF RAN FROM SOUTH SIDE MECHANICAL ROOM TO NORTH SODE MECHANICAL ROOM |