Permit: T09CM01053

Parcel: 140430130

Inspection Status: Approved

Inspection History: BUILDING - FINAL

Permit Number - T09CM01053

Inspection Description - BUILDING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
05/21/2010 BUILDING - FINAL Approved IVRS - Inspection :*
03/08/2010 BUILDING - FINAL Partial Approval IVRS - Inspection :*
1) FIRE C OF O AND SPRINKLER APPROVED
2) MECH AND PLUMBING, OK TO OCCUPY
03/04/2010 BUILDING - FINAL Partial Approval IVRS - Inspection :*
11/06/2009 BUILDING - FINAL Partial Approval IVRS - Inspection :*
1) PHASE II ROOM 124-126 OK WITH FIRE TO OCCUPY
09/21/2009 BUILDING - FINAL Partial Approval IVRS - Inspection :*
1) SPOKE WITH MECH, ELEC, PLUMBING AND FIRE OK WITH TEMP C OF OF FOR PHASE I
09/15/2009 BUILDING - FINAL Not ready for Inspection IVRS - Inspection :*
1) NEED ALL TRADE AND FIRE OK'S FOR TCO PHASE 1
2) OK WITH PLUMBING PHASE I MINUS AIR HANDLER
3) REMOVE CONSTRUCTION DEBRIS
4) EXIT SIGN S.W. LAB
5) ALL CORRIDORS AND EXITS NEED TO BE FREE OF CONSTRUCTION MATERIAL AND CLEAR