Inspection History Details
Inspection Status: Continued
Inspection History: STORMWATER INSTALL OF CONTROLS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/29/2014 | STORMWATER INSTALL OF CONTROLS | Continued | NO ACTIVITY | |
| 11/05/2013 | STORMWATER INSTALL OF CONTROLS | Approved | 1) SEDIMENT CONTROLS HAVE BEE INSTALLED ALONG THE PERIMETER OF THE SITE. 2) PLANTS IDENTIFIED ON THE NPPO PLAN HAVE BEEN TAGGED AND RE-PLANTED ON SITE |
|
| 10/01/2013 | STORMWATER INSTALL OF CONTROLS | Continued | 1) MET WITH SUPERINTENDENT TO DISCUSS STORM WATER, NPPO, AND GRADING REQUIREMENTS 2) CONTRACTOR WILL INSTALL SEDIEMNT CONTROLS PER THE APPROVED SWPPP 3) THE LANDSCAPE SUBCONTRACTOR WILL FLAG TREES TO BE PRESERVED AND TRANSPLANT TREES TO BE SAVED. 4) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED. 5) POST A COPY OF YOUR NOI AT THE ENTRANCE TO THE SITE 6) INSTALL AND USE A CONCRETE/MATERIALS WASH OUT AS NEEDED 7) SWEEP UP ANY TRACKED SOIL OFF ADJACENT ROADWAYS |