Inspection Status: Partial Pass
Inspection History: ENGR - Drainage Structures
Permit Number - DP22-0266
Inspection Description - ENGR - Drainage Structures
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/12/2024 | ENGR - Drainage Structures | Partial Pass | Concrete Ramp 10’ x 28’ located at the SW corner of building with 14” slab on grade reinforced with # 6 rebar 8” oc each direction on bottom of slab and # 5 rebar 12” oc each direction at top of slab is all present and ready for concrete pour. Concrete waste disposal storage slab 22’ x 28’ located at SE corner of building with 6” slab on grade with # 4 rebar 18” oc each direction is present and ready for concrete pour. |
|
01/19/2024 | ENGR - Drainage Structures | Partial Pass | North East corner of building 10’ x 35’ x 12” equipment pad all # 4 rebar 12”oc in both directions is present and ready for concrete pour on 01/22/24 | |
04/17/2024 | ENGR - Drainage Structures | Passed | ||
06/28/2023 | ENGR - Drainage Structures | Complete (Recurring) | Contractor called in for the wrongs inspection. Need to call in for building inspection. | |
08/18/2023 | ENGR - Drainage Structures | Not Ready | Connection to sewer on Sears and Ginger rd. to be inspected and approved by other permit. | |
11/16/2023 | ENGR - Drainage Structures | Partial Pass | (3) 10’x22’ entry ramps all rebar in place per plan and inspected by 3rd party (Terracon) ready for pour. (2) 10’x26’ entry ramps located on North side of building all rebar in place per plan and inspected by 3rd party (Terracon) ready for pour. |