Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 02/12/2026 |
ENGR Engineering Final
|
|
Passed |
|
| 09/22/2025 |
ENGR Engineering Final
|
|
Partial Pass |
contractor still installing all the landscape around the building |
| 09/25/2025 |
ENGR Engineering Final
|
|
Partial Pass |
Contractor needs to fix one of the handicap parking spaces because it’s noncompliant. I also need to put railing on the sidewalk that meets the right away sidewalk on the south end of the building need to complete all the landscaping throughout the project. |
| 09/29/2025 |
ENGR Engineering Final
|
|
Partial Pass |
Contractor has not addressed the handicap parking that’s not noncompliant and working on the sidewalk area that is noncompliant that is on the south side of the building from right away to private |
| 10/20/2025 |
ENGR Engineering Final
|
|
Partial Pass |
Contractor has not addressed the punchlist that we made up last week |