Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Paving
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/12/2026 | ENGR Paving | Passed | ||
| 08/22/2025 | ENGR Paving | Partial Pass | 08/22/25, 9:33 am, Compaction results are not being met. Tester is going to get a different machine. 08/25/25, After receiving a new proctor on 08/23/25, the go was given to proceeded with paving on the 25th of 08. |
|
| 11/19/2025 | ENGR Paving | Partial Pass | contractor called in the wrong inspection contractor needed to call in consultation inspection for the crosswalk on the north east corner from the building to the trash area in that crosswalk area noncompliance. Inform the contractor to get a letter from the engineer of record stating that he accepts the paving in that area . |