Inspection Status: Partial Pass
Inspection History: COT - ENGR - Stormwater
| Date |
Description |
Inspector |
Results |
Comments |
| 04/16/2024 |
COT - ENGR - Stormwater |
|
Partial Pass |
24 inch HDPE as shown |
| 04/16/2024 |
COT - ENGR - Stormwater |
|
Passed |
Redundant Inspection |
| 09/07/2023 |
COT - ENGR - Stormwater |
|
Partial Pass |
|
| 10/19/2023 |
COT - ENGR - Stormwater |
|
Partial Pass |
|
| 11/21/2023 |
COT - ENGR - Stormwater |
|
Partial Pass |
|
| 11/29/2023 |
COT - ENGR - Stormwater |
|
Partial Pass |
no issues or concerns at this time. All materials are contained within job site. |
| 12/13/2023 |
COT - ENGR - Stormwater |
|
Partial Pass |
|