Permit: DP21-0157

Parcel: 11620637A


Addresses:

165 S LINDA AV


Inspection Status: Complete (Recurring)

Inspection History: COT - ENGR - Stormwater

Permit Number - DP21-0157

Inspection Description - COT - ENGR - Stormwater

Inspection Status - Complete (Recurring)

Date Description Inspector Results Comments
03/26/2025 COT - ENGR - Stormwater Complete (Recurring) No concerns at this time
04/09/2025 COT - ENGR - Stormwater Partial Pass There is no water on the stormwater inspections as of yet contractor called in the wrong inspection
06/18/2025 COT - ENGR - Stormwater Complete (Recurring) there’s some wattles that need to be reinstalled on the north end of the project. Contractor is going to install catch basin on the north side, which has a lot of debris and trash in the hole that they have excavated to remove all the trash that’s in that hole before installing, the catch basin
06/30/2025 COT - ENGR - Stormwater Not Ready Contractors going to reschedule for tomorrow
08/13/2025 COT - ENGR - Stormwater Complete (Recurring) There’s no concerns at this time. Everything looks good.
08/27/2025 COT - ENGR - Stormwater Complete (Recurring) No concerns at this time. Everything looks good.
09/10/2025 COT - ENGR - Stormwater Complete (Recurring) No constraints at this time contractor seems to be maintaining the stormwater SWPPP.
10/08/2025 COT - ENGR - Stormwater Complete (Recurring) I had the contractor strengthen all the wattles. Everything looks pretty good. Informed the contractor we have some more rain this week to keep an eye on everything.
10/22/2025 COT - ENGR - Stormwater Complete (Recurring) No concerns at this time. Talk to the contractor he informed me that they’re forming up some ramps on the north end of the building and will call him for inspection tomorrow.
11/05/2025 COT - ENGR - Stormwater Complete (Recurring) Contractor removed all the wattles on the north end of the building informed the contractor he needs to put them all back along the fence line
11/19/2025 COT - ENGR - Stormwater Complete (Recurring) there’s no concern this morning with the stormwater follow up. There’s a piece of storm drain on the east side. The contractor is installing. I informed the contractor they needed a foot on either side of that stormwater pipe so they have to widen the trench.