Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Complete (Recurring)
Inspection History: COT - ENGR - Stormwater
Permit Number - DP21-0157
Inspection Description - COT - ENGR - Stormwater
Inspection Status - Complete (Recurring)
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/26/2025 | COT - ENGR - Stormwater | Complete (Recurring) | No concerns at this time | |
| 04/09/2025 | COT - ENGR - Stormwater | Partial Pass | There is no water on the stormwater inspections as of yet contractor called in the wrong inspection | |
| 06/18/2025 | COT - ENGR - Stormwater | Complete (Recurring) | there’s some wattles that need to be reinstalled on the north end of the project. Contractor is going to install catch basin on the north side, which has a lot of debris and trash in the hole that they have excavated to remove all the trash that’s in that hole before installing, the catch basin | |
| 06/30/2025 | COT - ENGR - Stormwater | Not Ready | Contractors going to reschedule for tomorrow | |
| 08/13/2025 | COT - ENGR - Stormwater | Complete (Recurring) | There’s no concerns at this time. Everything looks good. | |
| 08/27/2025 | COT - ENGR - Stormwater | Complete (Recurring) | No concerns at this time. Everything looks good. | |
| 09/10/2025 | COT - ENGR - Stormwater | Complete (Recurring) | No constraints at this time contractor seems to be maintaining the stormwater SWPPP. | |
| 10/08/2025 | COT - ENGR - Stormwater | Complete (Recurring) | I had the contractor strengthen all the wattles. Everything looks pretty good. Informed the contractor we have some more rain this week to keep an eye on everything. | |
| 10/22/2025 | COT - ENGR - Stormwater | Complete (Recurring) | No concerns at this time. Talk to the contractor he informed me that they’re forming up some ramps on the north end of the building and will call him for inspection tomorrow. | |
| 11/05/2025 | COT - ENGR - Stormwater | Complete (Recurring) | Contractor removed all the wattles on the north end of the building informed the contractor he needs to put them all back along the fence line | |
| 11/19/2025 | COT - ENGR - Stormwater | Complete (Recurring) | there’s no concern this morning with the stormwater follow up. There’s a piece of storm drain on the east side. The contractor is installing. I informed the contractor they needed a foot on either side of that stormwater pipe so they have to widen the trench. |