Inspection History Details
Inspection Status: Partial Pass
Inspection History
Permit Number - DP21-0157
Inspection Description -
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/13/2026 | Partial Pass | contractors good to pour the footing for the retaining wall on the north east quadrant of the project Contract is also good to pour the driveway apron on the north end |
||
| 08/22/2025 | Partial Pass | Retaining wall at North-west corner of building: footing placement, depth, and reinforcement are correct. Okay to pour footing. | ||
| 10/24/2025 | Partial Pass | Okay to grout first lift at NW ramp. | ||
| 10/30/2025 | Partial Pass | Contractor is good to grout retaining wall on the north side of the building and the retaining wall north east of the swimming pool area | ||
| 11/04/2025 | Partial Pass | Contractors good to grout the two walls at the north end of the building | ||
| 11/05/2025 | Partial Pass | Contractors good to grow the walls on the north east corner by the swimming pool | ||
| 12/02/2025 | Partial Pass | Contractor can start forming up for the manhole on the east side of the building for 30 inch drainage pipe | ||
| 12/23/2025 | Not Ready | Contractor needs to finish installing the vertical rods for the wall | ||
| 12/31/2025 | Partial Pass | Contractor and pour the footer for the retaining wall on the north end of the building across the street |