Inspection History Details
Inspection Status: Passed
Inspection History: ENGR - Drainage Structures
Permit Number - DP21-0157
Inspection Description - ENGR - Drainage Structures
Inspection Status - Passed
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/04/2025 | ENGR - Drainage Structures | Passed | Contractor damaged a 30 inch storm drain repaired it properly per City Of Tucson. | |
| 07/01/2025 | ENGR - Drainage Structures | Partial Pass | contractors good to pour the floors for the manhole north end of the building | |
| 07/02/2025 | ENGR - Drainage Structures | Partial Pass | Contractor continues to form up the top of the manhole number two | |
| 07/07/2025 | ENGR - Drainage Structures | Partial Pass | Contractors good to backfill storm drain number two | |
| 09/16/2025 | ENGR - Drainage Structures | Partial Pass | contract is good to backfill the 12 inch HD pipe into the 30 inch storm drain on the north east quadrant of the building. | |
| 10/03/2025 | ENGR - Drainage Structures | Partial Pass | Roof drain at NW corner of building: tie in to storm drain run A is good; okay to backfill. | |
| 10/24/2025 | ENGR - Drainage Structures | Partial Pass | okay to backfill CB adjacent to neighboring refuse enclosure on north east side of site. | |
| 10/28/2025 | ENGR - Drainage Structures | Partial Pass | Contractor is excavating for a 30 inch drain in the middle of the road north of the building. Will reschedule another inspection for tomorrow. | |
| 11/04/2025 | ENGR - Drainage Structures | Not Ready | Contractor is not ready to backfill the catch basin 1.2 1.3 and 1.4. Also for the contractor he needed to plate the trench ASAP. | |
| 11/06/2025 | ENGR - Drainage Structures | Partial Pass | Contractor is backfilling the basin at the north west corner of the project I had to come back at 10:30 this morning to check on the backfill because it’s 6:30am this morning. Contractor was not ready. | |
| 11/13/2025 | ENGR - Drainage Structures | Partial Pass | Contractor needs to be enforce the bottom of the great. When secured call in for a reinspection. | |
| 11/17/2025 | ENGR - Drainage Structures | Partial Pass | Contract is good to backfill the catch basin on the north west corner | |
| 11/18/2025 | ENGR - Drainage Structures | Partial Pass | Contractors good to backfill 30 inch HPDE pipe just south of the swimming pool 20 lineal feet | |
| 11/20/2025 | ENGR - Drainage Structures | Partial Pass | Rain day contractor did not work today | |
| 11/25/2025 | ENGR - Drainage Structures | Partial Pass | The contractor is good to pour the apron around the basin at the northwest corner of the project Contractor is also good to backfill the 30 inch HDPE pipe on the east end of the project |
|
| 12/01/2025 | ENGR - Drainage Structures | Partial Pass | contractors good to backfill the 30 inch HPDE pipe on the east side of the building.40 lf. |