Inspection Status: Not Ready
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 06/10/2022 |
ENGR Grading Final |
DROBERTS |
Not ready for Inspection |
Entered by VVERA1 - IS NOT READY AT THIS TME, THIS INSPECTION WAS CALLED FOR THE FLOOR SLAB OF THE NEW STORAGE UNITS, THEY WERE ADVISED TO CALL THE BUILDING INSPECTION TEAM TO SCHEDULE A SKYPE INSPECTION. |
| 07/29/2022 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by NGARCIA3 - Continued. Building progress only no site activity at this time.
|
| 05/24/2022 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN GRADING FOR PARKING LOT AND BUILDING PADS |
| 03/15/2023 |
ENGR Grading Final |
|
Passed |
|
| 03/15/2023 |
ENGR Grading Final |
|
Passed |
|
| 03/15/2023 |
ENGR Grading Final |
|
Passed |
|
| 11/30/2022 |
ENGR Grading Final |
|
Complete (Recurring) |
Contractor will send me over photos for the rebar for trash enclosure today |
| 12/16/2022 |
ENGR Grading Final |
|
Complete (Recurring) |
Inspected trash enclosure slab for the future poor, minor adjustments to the approach slab required an additional adobes underneath the rebar required photographs to follow showing corrections. |
| 12/16/2022 |
ENGR Grading Final |
|
Complete (Recurring) |
Inspected trash enclosure slab for the future poor, minor adjustments to the approach slab required an additional adobes underneath the rebar required photographs to follow showing corrections. |