Permit: DP19-0059

Parcel: 12404098A


Addresses:

947 N PARK AV

Inspection Status: Passed

Inspection History: ENGR Engineering Final

Date Description Inspector Results Comments
09/29/2021 ENGR Engineering Final MHERNANDEZ Approved Entered by NGARCIA3 - APPROVED
07/27/2021 ENGR Engineering Final BBENEDON Not ready for Inspection Entered by VLEON1 - Not ready. Project nearing completion
02/04/2021 ENGR Engineering Final BBENEDON Not ready for Inspection Entered by VLEON1 - NOT READY - COURTESY INSPECTION WITH DAVID ROBERTS AND SITE SUPERINTENDENT
10/19/2021 ENGR Engineering Final BBENEDON Approved Entered by NGARCIA3 - Approved
09/29/2021 ENGR Engineering Final MHERNANDEZ Continued Entered by NGARCIA3 - CN
07/23/2021 ENGR Engineering Final DROBERTS Not ready for Inspection Entered by RSALDAT1 - NOT READY AT THIS TIM
03/31/2021 ENGR Engineering Final DROBERTS Continued Entered by RSALDAT1 - CONTINUED, WORK MAINLY VERTICAL AT THIS TIME
03/31/2021 ENGR Engineering Final DROBERTS Continued Entered by VLEON1 - CONTINUED, WORK MAINLY VERTICAL AT THIS TIME
12/10/2019 ENGR Engineering Final BBENEDON Not ready for Inspection Entered by DMERANZ1 - This was an unscheduled inspection from John Vanwinkle‘s list.