Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Case: T15DV02299
Case Details
Entered Date:
03/25/2015
Applicant:
CATALINA INVESTMENTS LLC ATTN: MOISE HENDELES
Description:
APT FIRE; ALARM NUMBER F150840005.
Outstanding Inspections
Case Number: T15DV02299
Case Status: COMPLIAN
Case Description: FIRE AT COMMERCIAL BUILDING
Total Outstanding Inspections - 10
End Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/27/2015 | NPO(EL)-WIRING/SWITCH/OUTLT/FX | VIDAL | Follow-up inspection | |
11/27/2015 | NPO(PL)-PLUMBING SYSTEM & FX | VIDAL | Follow-up inspection | |
11/27/2015 | NPO(PL)-WATER HEATERS | VIDAL | Follow-up inspection | |
11/27/2015 | NPO(HC)-COOLING | VIDAL | Follow-up inspection | |
11/27/2015 | NPO(HC)-HEATING & VENTILATION | VIDAL | Follow-up inspection | |
11/27/2015 | NPO(DL)-DILAPIDATED STRUCTURE | VIDAL | Follow-up inspection | |
11/27/2015 | NPO - SMOKE ALARMS | VIDAL | Follow-up inspection | |
11/27/2015 | NPO - OTHER | VIDAL | Follow-up inspection | |
11/27/2015 | NPO - EXT. BUILDING MAINTENANC | VIDAL | Follow-up inspection | |
11/27/2015 | NPO - INT. BUILDING MAINTENANC | VIDAL | Follow-up inspection |
Completed Inspections
Case Status: COMPLIAN
Case Number: T15DV02299
Case Description: FIRE AT COMMERCIAL BUILDING
Total Completed Inspections - 2
End Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/25/2015 | INSP - INITIAL CODE ENFORCMENT | VIDAL | Approved | Received call from communication that T.F.D. on site with an apartment fire. Arrived and the fire was still be going and being worked on. Did check building to what building was on fire and was building #20. The power was turned off to building #18 and checked to have the power turned back on to let the occupants back into the units. The power was on and let the occupants back in. Building #23 had the power on and did check the units due to some had heat damage through the windows. Once it was determine that building #20 was going into fire watch, were able to let the tenants in into building #23 once all were checked. Some had cracked windows and the vinyl blinds were melted in the middle units of the building on 1st and 2nd floor. Building #20 had the power off and will remain off until the units are checked at daylight time. Due to the fire watch going to be done, was going to leave the site and will be called back once the fire watch is going to be removed and the investigation done. No fencing will be done until daylight. Did meet with the manager about the fire watch and was given permission to fence the property due to not able to find anyone to fence the area. Will meet the manager in the daylight time due to the fire watch. RV. |
11/27/2015 | INSP - FOLLOW UP CODE ENFORCE | VIDAL | Approved | No work has been done and met with management and they do not know the status of the work being done to the fire damage units. Will call the contractor. RV. |
Completed Activity Special Conditions
Case Description - FIRE AT COMMERCIAL BUILDING
Case Number - T15DV02299
Case Status: COMPLIAN
Total Completed Case Activity Conditions: 6
Date | Name |
12/01/2015 | CONTACTED BY PHONE |
04/14/2015 | CONTACTED IN PERSON |
04/14/2015 | NOTICE OF VIOLATION ISSUED |
11/16/2016 | VIOLATION CLOSED |
10/09/2015 | SEC LETTER OF BILLING FOR $??? SENT TO OWNERS |
04/09/2015 | STRUCTURE SECURED BY ??? |