Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T22CM05063
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/07/2022 | SAFEBUILT | 2ND PARTY REVIEW | REVIEW | Approv-Cond | Activity Number: T22CM05063 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: N/A BUILDING REVIEW COMMENTS: Approved MECHANICAL REVIEW COMMENTS: Conditionally Approved No mechanical plans submitted. no mechanical work is indicated in their scope of work approved/Subject to field approval ELECTRICAL REVIEW COMMENTS Conditionally Approved E1.01 ELECTRICAL DEMOLITION LIGHTING PLAN - AREA A: Comcheck implies that all of the 2x4 lighting is being removed, yet the Demo shows most of the 2x4 as (E.) (existing) which implies it is being left in place. Should correct before IFC. Comment applies to all lighting Demo sheets. PLUMBING REVIEW COMMENTS: Approved If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov |
| 10/12/2022 | JPEELDA1 | FIRE | REVIEW | Reqs Change | You shall provide a plan set that when expanded is legible to read You shall provide a written narrative letter of the operations in every area of the building from wood working, metal working, coating and so on. Provide a full Hazardous Material Inventory Statement (HMIS) Per IFC 2018, Chapter 50, Section 5001.5.2 Provide a Dust Hazard analysis (DHA) per IFC 2018, Chapter 22, Section 2003 We will not accept the wood combustible dust equipment as a deferred submittal, plans shall show the equipment for dust collection meets the requirement of IFC 2018, Chapter 22, Section 2203.3 & NFPA 654, 664. Provide MSDS and all quantities of chemicals being used throughout the buildings and define the operations in those areas. Define and explain how the refilling of the LD Resin & LD ISO refilling process will take place in the facility. Some Epoxy/Resins will only allow for foam and or water mist to be used in those areas for fire containment need better clarification of chemical to confirm proper extinguishment is being used. Will drying booths and or industrial ovens be added to the process? Provide a Hazardous Material Management plan per the IFC 2018, Chapter 50 Section 5001.5.1 (HMMP) Questions: Jennifer Peel-Davis Jennifer.Peel-Davis@Tucsonaz.gov 520-837-7033 Fire Plans Examiner Tucson Fire Department |