Permit Number: T22CM04003
Parcel: Unknown

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T22CM04003
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/11/2022 LEVANS2 ENGINEERING REVIEW Reqs Change Combo permits cannot be approved until their associated development package has been approved.

Lianne Evans
lianne.evans@tucsonaz.gov
10/13/2022 SAFEBUILT 2ND PARTY REVIEW REVIEW Reqs Change Activity Number: T22CM04003

GENERAL:
Provide written responses to all review comments.
Provide a complete plan set.
Provide additional documents as requested by review staff.


STRUCTURAL REVIEW COMMENTS:
Approved


BUILDING REVIEW COMMENTS:
Denied
Provide all document stamp/signed/dated by registered design professional. All mechanical sheets M000 through M200, 1 of 1 Site Photometric, 1 of 2 Building Photometric, 2 of 2 Building Photometric plans, are not stamp/signed/dated by registered design professional. (2018 IBC section 107)


MECHANICAL REVIEW COMMENTS:
Denied
1. Provide mechanical plans (IMC2018,106.3.1) Complied
2. Provide ventilation calculations (IMC2018,,403.3.1.1.1) you have 3,028 openable area for all your doors which will not meet the 4% openable area to the outdoors for natural ventilation. Not Complied
3. Provide a detailed narrative on the process that occurs in the warehouse (e.g. what materials are you storing in the warehouse, what type of forklifts are you using in the warehouse is it fuel or electric) (imc2018,106.3.1) Not Complied
4. Provide a written response to each correction along with the revised plans (MMC2015,106.3.1)


ELECTRICAL REVIEW COMMENTS
Conditionally Approved
E6.1 Electrical Panel Schedules: Panels NH 5 & 6 do not require 1000 amp buses.


PLUMBING REVIEW COMMENTS:
Denied
Third Plumbing Review:
1 thru 4 OK
5). Now that plumbing plans have been included, they need to be accompanied by the civil plans for water service & sewer continuation as stated on plumbing pages. -IPC 106.3.1


If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov
10/13/2022 PAUL CAMARENA ZONING REVIEW Reqs Change FROM: Paul Camarena
PDSD Zoning Review Section

PROJECT: T22CM04003 – Tucson Commerce Center
Building Plan Review (3rd Review)
6690 S Alvernon Wy / I-1
TRANSMITTAL DATE:?October 13, 2022


COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.


1. COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

2. COMMENT: Zoning has reviewed the building plans for compliance with the associated Development Package DP22-0149. Zoning cannot approve the building plans until the DP is approved.

If you have any questions about this transmittal, Contact Paul Camarena at (520)837-4986 or by email Paul.Camarena@tucsonaz.gov