Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T22CM04003
Parcel: Unknown

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T22CM04003
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
07/18/2022 DBENOIT1 2ND PARTY REVIEW REVIEW Reqs Change Activity Number: T22CM04003

GENERAL:
Provide written responses to all review comments.
Provide a complete plan set.
Provide additional documents as requested by review staff.


STRUCTURAL REVIEW COMMENTS:
Approved

BUILDING REVIEW COMMENTS:
Denied
Sheet A0.0 – Title sheet states MEP designers as “TBD” and designer responds that this permit is partial structural/architectural only and design will be submitted “7/11/22” so submit release for construction design documents. Coordinate MEP scopes with structural/architectural designs such as underground utilities and connections. Describe complete S/A and MEP scope of work in Sheet A0.0 project description and submit design documents prior to construction. (2018 IBC section 107)
Structural calculations – Cover sheet project address shows “6960” while drawings show “6690.” Which is it? Provide matching project address in all documents.

MECHANICAL REVIEW COMMENTS:
Denied
1. Provide mechanical plans (IMC2018,106.3.1) Not Complied
2. 2. Provide ventilation calculations (IMC2018,,403.3.1.1.1) you have 3,028 openable area for all your doors which will not meet the 4% openable area to the outdoors for natural ventilation. Not Complied
3. Provide a detailed narrative on the process that occurs in the warehouse (e.g. what materials are you storing in the warehouse, what type of forklifts are you using in the warehouse is it fuel or electric) (imc2018,106.3.1) Not Complied
4. there is no design build , there is only deferred submittals that must be noted on the construction documents on the cover sheet for deferred submittals


ELECTRICAL REVIEW COMMENTS
Denied
Electrical plans stated to be submitted as Design build by a contractor to be selected later.
Electrical cannot be approved without plans.


PLUMBING REVIEW COMMENTS:
Denied
Second Plumbing Review:
1 thru 3 Ok
4). SAME- No Building drain or water stub ins or any plumbing plans shown on these plans? - IPC 301.3


If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov
07/19/2022 SSHIELD1 COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Completed
07/19/2022 STEVE SHIELDS ZONING REVIEW Reqs Change FROM: PDSD Zoning Review Section

PROJECT: T22CM04003 – Tucson Commerce Center
Building Plan Review (2nd Review)
6690 S Alvernon Wy / I-1

TRANSMITTAL DATE: July 19, 2022

1. COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

2. COMMENT: Zoning has reviewed the building plans for compliance with the associated Development Package DP22-0149. Zoning cannot approve the building plans until the DP is approved.

If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov.
08/03/2022 JVINCEN1 FIRE REVIEW Approved
08/24/2022 SBLOOD1 ENGINEERING REVIEW Reqs Change The DP needs to be approved before the building plans can be approved.

Stephen Blood
(520) 837-4958
Stephen.blood@tucsonaz.gov