Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T22CM02751
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
07/08/2022 | SAFEBUILT | 2ND PARTY REVIEW | REVIEW | Reqs Change | Activity Number: T22CM02751 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: Approved BUILDING REVIEW COMMENTS: Approved MECHANICAL REVIEW COMMENTS: Denied1. The design submission accompanying the construction documents shall clearly detail procedures and methods to be used and the items subject to such inspections and tests .such commissioning shall be in accordance with generally accepted engineering practice , and where possible, based on published standards for the particular testing involved for the smoke control systems (IMC2018,513.3) Complied 2. A rational analysis supporting the types of smoke control systems to be employed, their method of operation, the systems supporting them and the methods of construction to be utilized shall accompany the submitted construction documents and shall include, but not limited to the items indicated in sections 513.4.1 through 513.4.7 (IMC2018,513.4) Complied 3. the owner or the owner’s authorized agent, other than the contractor, shall employ one or more approved agencies to provide special inspections and tests during construction on the types of work specified in Section 1705 and identify the approved agencies to the building official (IBC2018,1704.2) Complied 4. Approved agencies for smoke control testing shall have expertise in fire protection engineering, mechanical engineering and certification as air balancers and must be approved by the building official (IBC2018,1705.18.2) Complied 5. Provide the quantity of co2 being used for the beverage dispensers and method of protection (IFC2015,5307) Complied 6. Provide co2 piping plan (IMC2018,106.3.1) Complied 7. Provide manufacturers specs for the 2 kitchen hood and 1 type 2 dishwasher hood showing the minimum exhaust flow rate in cfm per linear foot, based on the cooking appliance duty classification as defined in the code (IMC2018,507.2.1) Not Complied this is a example of what I'm looking for to determine the exhaust rate for the hood which has the duty appliance and the cfm per linear foot of exhaust8. A report shall be submitted to the building official identifying the maximum expected quantities of hazardous materials to be stored, used in a closed system and used in an open system, and subdivided to separately address hazardous material classification categories based on Tables 307.1(1) and 307.1(2). The methods of protection from such hazards, including but not limited to control areas, fire protection systems and Group H occupancies shall be indicated in the report and on the construction documents. The opinion and report shall be prepared by a qualified person, firm or corporation approved by the building official and provided without charge to the enforcing agency. sheet 3P401E (IBC2018,414.1.3) It is strongly recommended that this report be provided as soon as possible the recommended agencies are Ino-tek out of Michigan or Jenson Hughes out of Chicago. in your code summary add this report to your deferred submittals. Complied 9. distinguish the difference in symbols, for the fire and smoke dampers, the fire damper and the smoke damper, in your mechanical legends page, their all the same, sheet 3M001 (IMC2018,106.3.1) Complied 10. Provide fire damper where duct penetrates the membrane of a roof/ceiling assembly sheet 3M201A (IMC2018,607.6.1) Complied 11. Provide fire damper where duct penetrates 2 hour fire barrier sheet 3M201A (IMC2018,607.5.2) Complied 12. Where multiple air handling systems share common return ducts with a combined design capacity greater than 2,000 cfm the return air system shall be provided with smoke detectors in a approved manner. sheet 3M201A (IMC2018,606.2.2) Not Complied 13. Provide fire and smoke damper where duct penetrates smoke barrier wall sheet 3M201B (IMC2018,607.5.4) Complied 14. Provide fire damper where duct penetrates the membrane of a roof/ceiling assembly sheet 3M201B (IMC2018,607.6.1) Complied 15. Provide fire damper where duct penetrates the membrane of a roof/ceiling assembly sheet 3M201C (IMC2018,607.6.1) Complied 16. Provide fire damper where duct penetrates the membrane of a roof/ceiling assembly sheet 3M201C (IMC2018,607.6.1) Complied 17. Provide fire damper where duct penetrates the membrane of a roof/ceiling assembly sheet 3M204C (IMC2018,607.6.1) Complied 18. Provide fire damper where duct penetrates the membrane of a roof/ceiling assembly sheet 3M204C (IMC2018,607.6.1) Complied 19. Provide fire and smoke damper where duct penetrates smoke barrier wall sheet 3M204D (IMC2018,607.5.4) Complied ELECTRICAL REVIEW COMMENTS Approved PLUMBING REVIEW COMMENTS: Denied Second Plumbing Review: 1 thru 3 OK 4).SAME- include interior storm piping plans with submittal -IPC 106.3.1, 1101.2 5 thru 14 OK 15). OK-Detail # 1 on plan page 3P702 needs to show a vacuum relief on each cold vertical drop @. each water heater. -IPC 504.2, 303.2 **Will need to be installed above water top, Field verify"" 16). Now that med gas storage cylinder relief valve terminations have been illustrated on plan page 3M202E, they are shown to be piped vertically all the way to the roof, these should be routed the shortest distance possible in a fashion not to restrict the flow. -NFPA99 5.1.3.5.6.1 , 5.1.3.5.6.4 (also see commentary). Suggest pipe to exterior wall and label If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov |
07/11/2022 | ROBERT SHERRY | WATER | REVIEW | Completed | |
07/13/2022 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
08/08/2022 | JPEELDA1 | FIRE | REVIEW | Approved |