| 10/11/2021 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet A3; First Floor Egress Plan: In the Wall Legend, a demising wall is indicated. Where is that wall type located on the plan? 2. Sheet A3 (First Floor Egress Plan); Sheet A5 (Hood Support Plan): The First Floor Egress Plan indicates a Section 4/A5 at new walls, while the Hood Support Plan indicates a Section 2/A5 at that same wall. Those two sections have different wall construction. Please clarify. 3. Sheet A5; Exhaust Hood Section: Metal studs are referenced at the back of the new hood. Are these metal studs new or existing? If new, indicate stud size, gauge, and spacing, and provide details for that wall as required. 4. Sheet A5; Exhaust Hood Section: Please provide a detail for the connection of the new (2)-2x12 beams to the metal stud wall. 5. Sheet A5; Detail 3: Please reference this anchor detail on the appropriate plan or detail. 6. General: Please provide written responses to all review comments. |
| 10/14/2021 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Provide additional details showing the construction of the "decorative metal cage" enclosing the new mechanical area, including clearances and sections. Reference: Section 107.2.1, IBC 2018. 2. Revise detail 103 to show how the grease exhaust duct and exhaust fan will be supported. Reference: Section 506.3.3, IMC 2018. 3. Show how safe maintenance access will be provided for the grease exhaust fan given its height above the roof surface and the proximity of the roof edge. Reference: Section 304.11, IMC 2018. |
| 10/14/2021 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Include all the gas-fired appliances in the natural gas piping design (e.g. the Cheesemelter). Reference: Section 402.1, IFGC 2018. |
| 10/14/2021 | ROBERT SHERRY | WATER | REVIEW | Completed | |
| 10/21/2021 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
| 10/21/2021 | SSHIELD1 | ENGINEERING | REVIEW | Passed | |
| 10/21/2021 | SSHIELD1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
| 10/22/2021 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the electrical plan review comments and also provide a written response. Designate branch circuits and panel for the branch circuits on the power floor plan. Locate the panels associated with this project on the power plans and correlate all the designated circuits and feeders, for the electrical equipment on the panel schedules. If any of the panels are new, provide a complete line diagram. Ref; 2018 IBC section 107.2.1, 2017 NEC. Tucson/Pima County Outdoor Lighting Code, City of Tucson Commercial Plan Submittal Requirements. |
| 11/08/2021 | JPEELDA1 | FIRE | REVIEW | Approved |