Permit: T21CM07828
Permit Details
Apply Date:
09/30/2021
Applicant:
Manuel Cordova
Description:
Kitchen Remodel
Permit Reviews
Permit Number - T21CM07828
Permit Status: Issued
Permit Description: Kitchen Remodel
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/30/2021 | COMMERCIAL - TI | 11/08/2021 | COMPLETED |
| 11/10/2021 | RESUBMITTAL | 12/07/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM07828
Permite Description: Kitchen Remodel
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/25/2022 | COT - FCON - Alarm - Final | N/A | Canceled | {Activity date: 08/25/2022; Status: Not Applicable; Inspector: Cgates; Comment: Entered by CGATES1 - } |
| 10/26/2022 | COT - ENGR - Site - Assurance Release | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM07828
Permit Description: Kitchen Remodel
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/19/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 01/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to cover progress areas.} | |
| 02/16/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 02/16/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved. In wall electric.} | |
| 02/16/2022 | COT - LCBU - Framing | Passed | {Activity date: 02/16/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved. Ok to insulate and cover walls} | |
| 02/16/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 02/16/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved} | |
| 07/19/2022 | COT - LCPL - Gas Pressure Test | Passed | {Activity date: 07/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 07/19/2022 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 07/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 07/19/2022 | COT - LCME - Kitchen Hood | Passed | {Activity date: 07/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/22/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VVERA1 - Partial. Duct system for hood assembly. Ok to double wrap duct and install.} | |
| 07/19/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 07/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 07/19/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 07/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/22/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VVERA1 - Partial. Duct work for Mechanical Hood above ceiling.} | |
| 07/19/2022 | COT - LCBU - Building Progress | Passed | {Activity date: 07/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 08/25/2022 | COT - LCME - Mechanical Final | Passed | {Activity date: 08/25/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} ; {Activity date: 07/27/2022; Status: Partial Approval; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF AIR BALANCE REPORT COMPLETED} ; {Activity date: 10/14/2021; Status: Prior to Final Inspectn; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - AIR BALANCE & HOOD PERFORMANCE REPORT REQUIRED} | |
| 08/25/2022 | COT - LCEL - Electrical Final | Passed | {Activity date: 08/25/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
| 08/25/2022 | COT - FCON - Sprinkler - Final | Passed | {Activity date: 08/25/2022; Status: Approved; Inspector: Cgates; Comment: Entered by CGATES1 - } | |
| 08/25/2022 | COT - FCON - Hood System - Final | Passed | {Activity date: 08/25/2022; Status: Approved; Inspector: Cgates; Comment: Entered by CGATES1 - } | |
| 08/25/2022 | COT - LCPL - Plumbing Final | Passed | {Activity date: 08/25/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/23/2022; Status: Partial Approval; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF WATER DISINFECTION REPORT COMPLETED} ; {Activity date: 10/14/2021; Status: Prior to Final Inspectn; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - WATER DISINFECTION REPORT REQUIRED} | |
| 08/26/2022 | COT - LCBU - Building Final | Passed | {Activity date: 08/26/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to make application for Certificate of Occupancy.} ; {Activity date: 08/25/2022; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by VVERA1 - Not ready. Need Fire Finals and Hood test } |
|
| 08/26/2022 | COT - FCON - Fire - Final | Passed | {Activity date: 08/26/2022; Status: Approved; Inspector: CGates; Comment: Entered by CGATES1 - } ; {Activity date: 08/25/2022; Status: Denied; Inspector: Cgates; Comment: Entered by CGATES1 - Signs for riser room and FACP, emergency lighting not working, Fire extinguishers hung, Extention cord removed from riser room. Report for sprinklers and alarm.} |