| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 07/07/2021 | JVINCEN1 | FIRE | REVIEW | Approved | |
| 07/14/2021 | SAFEBUILT | 2ND PARTY REVIEW | REVIEW | Reqs Change | Activity Number: T21CM05152 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: Denied 1. Provide accurate information regarding Current Codes per International Building Code 2018. The information provided in the Geotechnical Report is incorrect since State has adopted latest Codes. IBC 2012 and IBC 2015 are referenced for Site Class and Section 1605.3.2 under Seismic and Wind considerations of the report. Revise Geotechnical Report and resubmit. 2. The Earthquake Design Data parameters used in Structural Calculations (page 1) and shown on the Structural Drawing S0.1 do not match. Make necessary revisions and resubmit. 3. Verify Footing Mark F2 at 2/A and 2/N. Why these Footings are smaller than Footings at 6/A and 6/N with similar loading. Submit a response letter addressing these correction items and provide bubbles on the revisions to the drawings. BUILDING REVIEW COMMENTS: Denied 1. They typical exit plans do not show exiting distances. Provide these measurements. MECHANICAL REVIEW COMMENTS: Denied 1.PROVIDE INFORMATION ON HOW YOU ARE GOING TO PROTECT THE WET PIPE FIRE SPRINKLER IN THE WAREHOUSE FROM FREEZING (NFPA13,8.16..4.1.1) ELECTRICAL REVIEW COMMENTS Approved PLUMBING REVIEW COMMENTS: Approved |
| 07/14/2021 | ROBERT SHERRY | WATER | REVIEW | Completed | |
| 07/16/2021 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | ZONING REVIEW TRANSMITTAL FROM: PDSD Zoning Review PROJECT: T21CM05152, 5153, 5154 & 5155 2636 E Ginter Rd New Buildings TRANSMITTAL: July 16, 2021 This site is located in the I-1 zone (UDC 4.7.29). General Manufacturing is a permit use in the zone (Table 4.8-5) subject to Use Specific Standards 4.9.5.C.2, .6, .7, & .8 and 4.9.13.Q. 1. Provide fully dimensioned elevation with the next submittal so that heights can be verified. 2. Zoning has reviewed the building plans for compliance with DP21-0113 and although the building plans appear to match the tentative plat until tentative plat DP21-0113 and final plat S21-031 have been approved and recorded zoning cannot approve the building plans. If you have any questions about this transmittal, please contact Elisa Hamblin at Elisa.Hamblin@tucsonaz.gov. |
| 07/16/2021 | SSHIELD1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Approved | |
| 07/29/2021 | SBLOOD1 | ENGINEERING | REVIEW | Reqs Change | The DP needs to be approved before the building plans can be approved. Stephen Blood (520) 837-4958 Stephen.blood@tucsonaz.gov |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 07/29/2021 | VVERA1 | OUT TO CUSTOMER | Completed |