Permit Number: T21CM04815
Parcel: 110035860

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T21CM04815
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
07/19/2021 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. A note requiring the contractor to design a structure and to evaluate the strength of a wall is not appropriate. [Initial comment: Provide a design for the mounting shelf for the water heater along with structural calculations to show that the water heater is safely supported from the building structure. Reference: Section 301.2, IPC 2018.]
2. Comment not resolved; the detail still shows the expansion tank installed on the hot water pipe. [Initial comment: Revise detail 5/P5.0 to show the expansion tank installed correctly and in a manner consistent with the Code and the manufacturer’s instructions (i.e. install the expansion tank on the cold-water service to the water heater). Reference: Section 303.2, IPC 2018.]
3. Comment not resolved; the cold-water supply to the water heater does not have a full-open shutoff valve. [Initial comment: Provide a full-open valve for the water supply pipe to the water heater. Reference: Section 606.1(8), IPC 2018.]
4. Comment not resolved; detail 5/P5.0 still shows a shutoff valve located between the water heater and the expansion tank. [Initial comment: The design of the water heater piping, as shown in detail 5/P5.0, with a shutoff valve located between the water heater and the expansion tank, makes it impossible for the expansion tank to accommodate the thermal expansion of the water in the water heater, as intended by Section 607.3, IPC 2018. Reference: Section 303.2, IPC 2018.]
07/19/2021 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Comment not resolved; ten copies of an incomplete COMcheck Envelope Compliance report is unacceptable. [Initial comment: The portion of the building shell being modified in this activity does not appear to have been conditioned. Section C503.2, IECC 2018 requires the space to be brought into full compliance with the current energy code. Demonstrate energy code compliance for the building envelope, HVAC, and interior lighting using calculations based on the current code. Reference: Sections C101.5, C103.2, C303, and C401.2, International Energy Conservation Code 2018.]
2. Coordinate the heating and cooling load calculations with the zoning shown on the mechanical floor plan for HP-5 and HP-6. [Initial comment: Provide heating and cooling load calculations to justify the heating/cooling capacities of the specified HVAC units. Reference: Section C403.1.1 and C403.3.1, IECC 2018.]
07/19/2021 ROBERT SHERRY WATER REVIEW Reqs Change Section 604.1, IPC 2018 allows water distribution systems to be designed using accepted engineering methods. Your calculations do not appear to be based on any accepted engineering method. Determine the water demand using an accepted engineering method such as the methods shown in Appendix E, IPC 2018. [Initial comment: Provide the size of the water meter serving this address, the size of the backflow preventer associated with the water meter, and the total water demand served by the water meter. Reference: Section 107.2.1, IBC 2018.]
07/27/2021 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Approved