Permit: T21CM04815
Permit Details
Status:
L of c
Type:
COMMERCIAL ALTERATION
Address:
3925 E FORT LOWELL RD 104
Address NEW:
3925 E FORT LOWELL RD 104
Apply Date:
06/09/2021
Applicant:
Burton and Associates Architects, LLC
Description:
TI: OFFICE
Architects:
- Richard Burton
Contractors:
- Rio West Developers & Constuction, Inc.
Permit Reviews
Permit Number - T21CM04815
Permit Status: L of c
Permit Description: TI: OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/09/2021 | COMMERCIAL - TI | 07/12/2021 | COMPLETED |
| 07/14/2021 | RESUBMITTAL | 07/27/2021 | COMPLETED |
| 09/03/2021 | RESUBMITTAL | 09/08/2021 | COMPLETED |
| 09/28/2021 | RESUBMITTAL | 09/30/2021 | COMPLETED |
Completed Inspections
Permit Status: L of c
Permit Number: T21CM04815
Permit Description: TI: OFFICE
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/08/2021 | PLUMBING - FINAL | RSHERRY | Approved | WATER DISINFECTION REPORT REQUIRED |
| 09/30/2021 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
| 10/12/2021 | PLUMBING - ROUGH, SOIL | WGALLAGHER | Approved | Approved |
| 11/09/2021 | ELECTRIC - INTERMEDIATE | WGALLAGHER | Approved | Partial approval several outlets no ground made |
| 11/09/2021 | PLUMBING - INTERMEDIATE | WGALLAGHER | Approved | Approved |
| 11/09/2021 | MECHANICAL - INTERMEDIATE | WGALLAGHER | Approved | Not ready |
| 11/09/2021 | FRAMING | WGALLAGHER | Approved | Partial approval ok to install hard lids and two side walls, need several lateral braces at TOW |
| 01/11/2022 | ELECTRIC - SERVICE UPGRADE | ESTEVENS | Approved | N/A |
| 01/11/2022 | ELECTRIC - OUTDOOR LIGHTING | ESTEVENS | Approved | N/A |
| 01/11/2022 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | N/A |
| 01/11/2022 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | Approved |
| 01/11/2022 | BUILDING ABOVE CEILING | ESTEVENS | Approved | Approved |
| 01/19/2022 | FIRE - FINAL | CBASALDUA | Approved | |
| 01/19/2022 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 01/19/2022 | ELECTRIC - FINAL | JBURGE | Approved | Approved |
| 01/19/2022 | BUILDING - FINAL | JBURGE | Approved | Approved |
| 01/19/2022 | BUILDING - PROGRESS | JBURGE | Approved | Approved |