Permit Number: T19CM05738
Parcel: 11451218A

Review Status: Completed

Review Details: COMMERCIAL - NEW

Permit Number - T19CM05738
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/13/2019 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Reqs Change Please address the following electrical plan review comments. Also provide a written response.
1. Correlate the power requirements for the water heater with the water heater schedule shown on the plumbing plan, (208 volts).
Ref; 2018 IBC sec 107.2.1, 2017 NEC.
09/13/2019 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. Provide the architectural anchoring details for the proposed stand for the water heater as noted in detail 201. Reference: Section 107.2.1, IBC 2018.
2. The horizontal drain from the lavatory P-1 discharges to the vent for P-2. A plumbing vent may not be used for any purpose other than venting of the plumbing system. Revise the lavatory horizontal drain to connect to the horizontal drain downstream of the water closet connection. Alternatively, the lavatory could be common-vented with the water closet by removing the 1-1/2" vent for the lavatory. Reference: Sections 901.4 and 911.3, IPC 2018.
3. Provide an independent secondary roof drain for the storage building on sheet A.8; the discharge point of the secondary roof drain shall be separate from the primary roof drain per Section 1108.2, IPC 2018
09/13/2019 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Clarify the component descriptions in the COMcheck envelope compliance certificate. The thermal envelope in question appears to be the reception, office, and restrooms in the building. The description of wall type W6 doesn't appear to be complete: what insulation R-value is being installed in the furred out areas? Wall type W1 doesn't terminate at the underside of the structure, leaving an uninsulated opening in the thermal envelope. Reference: Section 107.2.1, IMC 2018 and Section 103.2.1, IECC 2018.
2. Specify the intended R-value for the foam insulation on the roof. Reference: Section 103.2, IECC 2018.
09/13/2019 PAUL CAMARENA ZONING REVIEW Reqs Change FROM: Paul Camarena
PDSD Zoning Review Section

PROJECT: T19CM05738
Building Plans (1st Review) Brake Max
9191 E Tanque Verde Rd - Related to DP19-0191

TRANSMITTAL DATE: September 13, 2019

DUE DATE: September 9, 2019

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.


01. COMMENT: Zoning has reviewed the plan and cannot approve at this time. Please address the following comments.


02. COMMENT: Zoning cannot approve until Development Package is approved.





If you have any questions about this transmittal, Contact Paul Camarena any time during the week at (520) 837-4082 or by email Paul.Camarena@Tucsonaz.gov or contact Steve Shields any time during the week at (520) 837-4956 or email Steve.Shields@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised Building Plans
09/13/2019 ROBERT SHERRY WATER REVIEW Completed
09/13/2019 LOREN MAKUS ENGINEERING REVIEW Reqs Change Development Package DP19-0191 must be approved first.
09/16/2019 ENEWCOM1 FIRE REVIEW Approved
09/16/2019 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. Sheet G.1; Code Review (Occupant Loads): The Repair Garage portion indicates 200 SF/occupant. Please clarify, using the IBC Table 1004.5, how the occupant load factor was determined. It would appear the Industrial function (100 SF/occupant for gross area) would be most likely. Please verify.
2. Sheet G.1; Code Review (Occupant Loads): The Front Customer Service Area portion indicates 50 SF/occupant. Please clarify, using the IBC Table 1004.5, how the occupant load factor was determined. It would appear the Assembly function (15 SF/occupant for net area) would be most likely. Please verify.
3. Sheet G.1; Code Review (Occupant Loads): The Customer Waiting Room portion indicates a number of seats for the occupant load determination. Please clarify, using the IBC Table 1004.5, how the occupant load factor was determined. It would appear the Assembly function (15 SF/occupant for net area) would be most likely. Please verify.
4. Sheet G.1; Code Review: Please provide on this sheet the required plumbing fixture calculations per the IBC Section 2902.1.1.
5. Sheet A.1; Keynotes: Please indicate on Note 5 that the service counter shall meet the requirements of the ICC/ANSI Section 904.
6. Sheet A.1; Floor Plan: Keynote 7 was not located on the plan. Please verify.
7. Sheet A.1; Keynotes: Note 19 does not seem to match the location indicated on the plan (Garage 106). Please verify.
8. Sheet A.1; Keynotes: Note 21 references a recess in the floor slab. Please provide a detail for that recess.
9. Sheet A.1.1; Mounting Heights: Please reference Sheet A.7 for the restroom grab bar mounting heights.
10. Sheet A.2; Keynotes: Note 1 indicates a wood framed awning. Please add a reference in that note to Sheet S.2 for that awning.
11. Sheet A.5; Detail 7: Per the IBC Section 1011.12.2 (Exception), the roof hatch required is larger than that provided on the detail. Please verify.
12. Sheet S.1; Foundation Plan: Keynote 4 was not located on the plan, and MCJ was also not indicated. Please verify.
13. Sheet S.1; Foundation Plan: Keynote 3 was not located on the plan. Please verify.
14. Sheet S.2; Section 7: Were structural calculations for this awning included with this permit? Please verify.
15. Sheet S.4 (Roof Framing Plan); Structural Calculations (Sheet 98): The calculations indicate 2x8 roof joists at 24" o.c., while the framing plan indicates 2x6 at 24" o.c. Please coordinate.
16. General: Please provide the Special Inspections Certificate with Parts A and B completed.
17. General: Please provide written responses to all review comments.

Review by Eric Newcomb
Contact at 520-837-4911 or Eric.Newcomb@tucsonaz.gov
09/16/2019 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
09/17/2019 QJONES1 APPROVAL SHELF Completed
09/17/2019 QJONES1 OUT TO CUSTOMER Completed
09/17/2019 QJONES1 REJECT SHELF Completed