Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
9191 E TANQUE VERDE RD
Apply Date:
08/09/2019
Applicant:
N/A
Description:
BUILD NEW AUTO SERVICE BUILDING
Architects:
  • CAPPS, ANTHONY G
Contractors:
  • MW MORRISSEY CONSTRUCTION LLC

Permit Reviews

Permit Number - T19CM05738
Permit Status: C of o
Permit Description: BUILD NEW AUTO SERVICE BUILDING
Start Date Submittal Complete Date Status  
01/09/2020 RESUBMITTAL 03/03/2020 COMPLETED Review Details
03/03/2020 REVISION - - 1ST 04/09/2020 COMPLETED Review Details
08/09/2019 PLANS OK TO SUBMIT - COMM 08/12/2019 COMPLETED Review Details
08/13/2019 COMMERCIAL - NEW 09/17/2019 COMPLETED Review Details
09/17/2019 RESUBMITTAL 10/11/2019 COMPLETED Review Details
10/11/2019 RESUBMITTAL 01/09/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T19CM05738
Permit Status: C of o
Permit Description: BUILD NEW AUTO SERVICE BUILDING
Total Outstanding Activity Conditions - 1
Date Name
08/09/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T19CM05738
Permit Description: BUILD NEW AUTO SERVICE BUILDING
Total Completed Inspections - 33
Date Description Inspector Results Comments
10/03/2019 PLUMBING - FINAL RSHERRY Approved WATER DISINFECTION REPORT REQUIRED
10/03/2019 MECHANICAL - FINAL RSHERRY Approved AIR BALANCE REPORT REQUIRED
02/03/2020 PLUMBING - SEWER HCS CONNECT MRAMBER Approved Tie in at existing to back water valve ok on test.
02/07/2020 ELECTRIC - UFER MRAMBER Approved
02/13/2020 PLUMBING - BACK WATER VALVE MRAMBER Approved
02/19/2020 PLUMBING - ROUGH, SOIL RCHANDLER Approved
02/19/2020 EXCAVATION/LAYOUT REBAR & ZON RCHANDLER Approved
02/26/2020 BUILDING PRE-SLAB RCHANDLER Approved Via pictures.
03/11/2020 STEM WALL/RETAINING WALL RCHANDLER Approved
03/31/2020 ELECTRIC - UNDERGROUND DMUNIZ Approved secondary Conduits from Transformer to Location of new CT can ok to shade, tape, and backfill.
RVI
04/01/2020 PLUMBING - YARD WTR LINE/TEST DMUNIZ Approved
04/27/2020 REINFORCED MASONRY PRE-GROUT WGALLAGHER Approved fifth and final lift is ok for grout
05/08/2020 ROOF NAILING WGALLAGHER Approved
05/18/2020 FRAMING WGALLAGHER Approved Approved ok to one side drywall
05/18/2020 ELECTRIC - INTERMEDIATE WGALLAGHER Approved
05/21/2020 PLUMBING - INTERMEDIATE DMUNIZ Approved Hot water lines insulated and under test ok to proceed.
05/22/2020 PLUMBING - ROOF DRAINS WGALLAGHER Approved
06/04/2020 TEP CLEARANCE - PM TTEMBULAK Approved CODE ECO
06/04/2020 ELECTRIC - CONSTRUCTION POWER TTEMBULAK Approved Clearance for TEP ECO called in to Marcia at 8:35
06/05/2020 STUCCO MESH TTREMBULAK Approved
06/23/2020 MECHANICAL - INTERMEDIATE TTREMBULAK Approved Approved
06/23/2020 PLUMBING - ABOVE CEILING TTREMBULAK Approved Approved
06/23/2020 ELECTRIC - ABOVE CEILING TTREMBULAK Approved Approved
06/23/2020 U VALUE FOR WINDOW TTREMBULAK Approved Approved
06/23/2020 BUILDING ABOVE CEILING TTREMBULAK Approved Approved
07/06/2020 FIRE - FINAL MRoss Approved
07/06/2020 OUTDOOR LIGHTING FINAL TTREMBULAK Approved Approved
07/06/2020 ELECTRIC - FINAL TTREMBULAK Approved Approved
07/06/2020 ELECTRIC - OUTDOOR LIGHTING TTREMBULAK Approved Approved
07/06/2020 BUILDING - PROGRESS TTREMBULAK Approved Approved
07/08/2020 BUILDING - FINAL RSALDAT1 Approved ENGINEERING FINAL STATUS. FINAL PERMIT.
07/08/2020 ENGINEERING - FINAL DROBERTS Approved IS APPROVED
07/08/2020 BUILDING - FINAL WGALLAGHER Approved See previous inspection results 7/6/20: PENDING ENGINEERING FINAL.