Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Permit Number - T19CM05657
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/30/2019 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet S1; General Structural Notes (Building Code): Please revise the Building Code to the 2018 Edition, and verify all requirements of that code are met. 2. Sheet S1; General Structural Notes (Foundations): Add verbiage to the drilled pier note to reference the Soil Report Table in Section 7.1 for drilled pier capacities. 3. Sheets S2 through S5 (Plans); Sheet PV-1 (Overview Plan): On Sheet PV-1, the new parking canopies are identified as A through M, while Sheets S2 through S5 identify the canopies as 1 through 13. Please coordinate. 4. Structural Calculations; Page 3 (Building Code): Please revise the Building Code to the 2018 Edition, and verify all requirements of that code are met. 5. Structural Calculations; Page 20: A boxed note indicates this analysis (14" deep purlin) is for a 27' span. The analysis indicates a 30' span. Please clarify. 6. Structural Calculations; Page 63: This frame indicates a W14x53 column and a W12x50 beam. Where is this frame? Please clarify. 7. Structural Calculations: Please coordinate the structural calculations 1 through 13 with the plans (Canopies A through L). 8. General: Please provide written responses to all review comments. Reviewed by Eric Newcomb Contact at 520-837-4911 or Eric.Newcomb@tucsonaz.gov |
09/06/2019 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. 1. Reference plan sheet PV-4.4; The PV SWITCHBOARD 'SB-01' must be listed as suitable for use as service equipment, per NEC 690.13C. 2. Verify the exterior lighting is rated as full cut off shielding and installed so as to not compromise the full cut off effect. Section 401.2.1(4). Ref; 2018 IBC sec 107.2.1, 2017 NEC, 2012 Tucson/Pima County Outdoor Lighting Code. |
09/11/2019 | MROSS2 | FIRE | REVIEW | Approved | |
09/13/2019 | LOREN MAKUS | ENGINEERING | REVIEW | Reqs Change | The propose solar canopies will be within an established retention/detention basin and drainage facility. A development package and drainage statement are required to demonstrate no adverse impact on the functioning of the basin and on the adjacent properties. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
09/23/2019 | SBORZAK1 | OUT TO CUSTOMER | Completed |