Permit Review Detail
Review Status: Completed
Review Details: PLANS OK TO SUBMIT - COMM
Permit Number - T19CM05188
Review Name: PLANS OK TO SUBMIT - COMM
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
07/23/2019 | SSHIELD1 | ADA | REVIEW | Passed | |
07/23/2019 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | PDSD TRANSMITTAL FROM: Steve Shields Section Manager PROJECT: Panera - Remodel & Drive-Thru T19CM05188 Building Plan (1st Review) TRANSMITTAL DATE: July 23, 2019 1. The building plans have been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. The building plans have been reviewed for compliance with development package DP18-0153 and although it appears that the building plans meet the requirements of DP18-0153 Zoning cannot approve the building plans until the following comments are addressed. 3. The development package sheets provided in the building plans either need to be the stamped and approved plans, marked as "REFERENCE ONLY" or they need to be removed from the building plan set. 4. The development package, DP18-0153 will need to be issued prior to issuing the building permit. 5. Until the building plan is approved by all other review agencies Zoning cannot approve the plan. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 |
07/25/2019 | LOREN MAKUS | ENGINEERING | REVIEW | Passed | |
07/26/2019 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
07/26/2019 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Needs Review | |
07/26/2019 | ENEWCOM1 | FIRE | REVIEW | Needs Review |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
08/05/2019 | QJONES1 | APPROVAL SHELF | Completed |
08/05/2019 | QJONES1 | OUT TO CUSTOMER | Completed |
08/05/2019 | QJONES1 | REJECT SHELF | Completed |