Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T19CM01757
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/17/2019 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. 1. As requested at the previous plan review comment #2 for power and lighting outlets for the above ceiling FC units. The NEC requires a receptacle and switched lighting outlet. Also designate a branch circuit and panel. NEC 210.63, 210.70A(3). 2. As requested at the previous plan review comment #3. The City of Tucson does not recognize as builds. As requested, please provide designated branch circuits and panels, include switching for the lighting as required per the 2018 IECC. Ref: 2018 IBC sec 107.2.1, 2018 IECC, 2017 NEC, City of Tucson Commercial Plan Submittal Requirements. |
05/17/2019 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Passed | |
05/17/2019 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | The total and sensible cooling capacities for rooftop units RTU-1, 2, 3, 5, 6, 8, and 10 appear to be greater than required based on the cooling load calculations. Verify the unit selections. Reference: Section C403.1.1, IECC 2018. [Second comment: The calculations only show the sensible cooling loads and the schedule only shows the total cooling capacity of the units. Please add a bit more information.] [Initial comment: Provide heating and cooling load calculations to justify the heating/cooling capacities of the specified rooftop units. Reference: Section C403.1.1 and C502.2.3, IECC 2018.] |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
06/28/2019 | QJONES1 | APPROVAL SHELF | Completed |
06/28/2019 | QJONES1 | OUT TO CUSTOMER | Completed |