Permit Number: T18CM07011
Parcel: 11809039B

Review Status: Completed

Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG

Permit Number - T18CM07011
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/29/2019 AVAUGHN1 OIP REVIEW Passed n/a
09/25/2018 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. Sheet S1 (Roof Framing Plan); Structural Calculations (Page 4): The calculations indicate the roof slab requires #4 at 9" o.c. each way. The roof framing plan indicates #5 at 8" o.c. (bottom in east/west direction), but #4 at 12" o.c. bottom in the north/south direction. Please verify.
2. Sheet S1; Floor Plan: Keynote 7 is not indicated on this plan. Please verify.
3. Sheet S1; Foundation Plan: Note 5 indicates a step foundation. Please provide a detail on these drawings for that condition.
4. Sheet S1; Building Elevation Keynotes: Note 6 was not located on the elevations. Please verify.
5. Sheet S1; Building Elevation Keynotes: Note 8 was not located on the elevations. Please verify. The note does reference 4/S2 for the detail.
6. Sheet S2; Building Section 1B: Please indicate on this section the 2-#4 top and bottom (match note in A).
7. Sheet S2; Sections 2 and 3: The keynotes on these sections indicate stepped footings. Please revise.
8. Sheet S3; Concrete Base Detail 1: Is a structural calculation provided for this foundation? Please verify.
9. General: Please provide a Special Inspection Certificate with Parts A and B completed.
10. General: Please provide written responses to all review comments.

Reviewed by Eric Newcomb
Contact at 520-837-4911
09/25/2018 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
10/01/2018 DAVID RIVERA ZONING REVIEW Reqs Change FROM: David Rivera
PDSD Zoning Review Section

PROJECT: T18CM07011 - Tucson Water Electrical Control Building.
Building plans (1st Review)
1580 S Santa Cruz Lane - R-1 Zoning

TRANSMITTAL DATE: October 1, 2018

DUE DATE: October 4, 2018

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.


1. COMMENT: Zoning has reviewed the building plans but cannot approve them at this time. (Due to the R-1 zoning of the parcel the proposed use is not a use that is allowed by without processing a special exception.) The proposed on this parcel is considered a Utility Use - Distribution System and requires approval through a Special Exception Process and submittal of a Development Package. As this use will be a COT owned and operated facility and site, it may be beneficial to request a City Manager Waiver to the Special Exception and DP through the PDSD Director. Contact Steve Shields at 837-4956 or Steve.Shields @tucsonaz.gov for information on the waiver request.

2. COMMENT: In addition, the building plans must be approved by the PDSD commercial plans reviewers before zoning can approve the plans.

3. COMMENT: Once the plans have been approved by all Commercial Plans reviewers and no site changes are made that affect zoning requirements, zoning will stamp and sign the building plans as it pertains to the zoning review purview.

4. COMMENT: If a City Manager Waiver is requested and granted, include with the next submittal the signed waiver documentation and if applicable incorporate any conditions of the waiver into the drawings.

If you have any questions about this transmittal, Contact David Rivera on Tuesday or Wednesday at (520) 837-4957 or by email at David.Rivera@tucsonaz.gov or contact Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov
10/03/2018 MARTIN BROWN FIRE REVIEW Approved
10/04/2018 JOHN VAN WINKLE ENGINEERING REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
01/29/2019 AVAUGHN1 APPROVAL SHELF Completed
01/29/2019 AVAUGHN1 OUT TO CUSTOMER Completed
01/29/2019 AVAUGHN1 REJECT SHELF Completed