Permit Details

Status:
Final
Type:
COMMERCIAL NEW
Address NEW:
1580 S SANTA CRUZ LN
Apply Date:
09/06/2018
Applicant:
MICHAEL MOURREALE
Description:
ELECTRICAL CONTROL BUILDING FOR TUCSON CITY WATER
Contractors:
  • ASHTON COMPANY INC CONTRACTORS *T

Permit Reviews

Permit Number - T18CM07011
Permit Status: Final
Permit Description: ELECTRICAL CONTROL BUILDING FOR TUCSON CITY WATER
Start Date Submittal Complete Date Status  
01/29/2019 RESUBMITTAL 01/29/2019 COMPLETED Review Details
01/29/2019 RESUBMITTAL 01/31/2019 COMPLETED Review Details
09/06/2018 PLANS OK TO SUBMIT - COMM 09/06/2018 COMPLETED Review Details
09/06/2018 COMMERCIAL - BLDG/FIRE/ZONING/ENG 01/29/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM07011
Permit Status: Final
Permit Description: ELECTRICAL CONTROL BUILDING FOR TUCSON CITY WATER
Total Outstanding Activity Conditions - 1
Date Name
09/06/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T18CM07011
Permit Description: ELECTRICAL CONTROL BUILDING FOR TUCSON CITY WATER
Total Completed Inspections - 16
Date Description Inspector Results Comments
02/14/2019 ELECTRIC - UNDERGROUND MHASSAN Approved
02/28/2019 ELECTRIC - UFER MHASSAN Approved
05/02/2019 TEP CLEARANCE - PM MHASSAN Approved CODE ECO
05/02/2019 ELECTRIC - SERVICE UPGRADE MHASSAN Approved OK to clear electric ECO. This is for new service for a water chlorination facility.
05/02/2019 ELECTRIC - CONSTRUCTION POWER MHASSAN Approved
05/02/2019 ELECTRIC - TEMPORARY SERVICE MHASSAN Approved
06/17/2019 ELECTRIC - PROGRESS MHASSAN Approved
06/17/2019 ELECTRIC - INTERMEDIATE MHASSAN Approved
06/17/2019 ELECTRIC - FINAL MHASSAN Approved
06/19/2019 REINFORCED MASONRY PRE-GROUT JGARCIA Approved Special Inspection report accepted. COT inspection was not called in.
06/19/2019 BUILDING PRE-SLAB JGARCIA Approved Special Inspection report accepted. COT inspection was not called in.
06/19/2019 EXCAVATION/LAYOUT REBAR & ZON JGARCIA Approved Special Inspection report accepted. COT inspection was not called in.
06/20/2019 OUTDOOR LIGHTING FINAL TVALENCIA Approved
06/20/2019 ELECTRIC - OUTDOOR LIGHTING TVALENCIA Approved
06/20/2019 BUILDING - FINAL TVALENCIA Approved
06/20/2019 ENGINEERING - FINAL BBENEDON Approved