Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Permit Number - T18CM04910
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 07/02/2018 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 07/10/2018 | ERIC NEWCOMB | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | PV4.0 Indicate the size of the bonding jumper from the neutral lug to the CT CABINET. NOTICE FOR INSPECTOR: The 3-line drawing shows a supply-side connection for the photovoltaic system. A field inspection by an NRTL to RE-LIST the Sevice equipment may be necessary after the supply side tap is performed. |
| 07/10/2018 | GPERU1 | BUILDING-COMMERCIAL | REVIEW | Approv-Cond | 1. Designate specific qualified individuals for the Special Inspections required for this project. IBC 1704.1 |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 08/09/2018 | AVAUGHN1 | OUT TO CUSTOMER | Completed |
| 08/09/2018 | AVAUGHN1 | REJECT SHELF | Completed |