Permit: T18CM04910
Permit Details
Apply Date:
06/22/2018
Applicant:
WILSON ELECTRIC SERVICES CORP ** APA **
Description:
COMMERCIAL SOLAR INSTALL
Contractors:
- WILSON ELECTRIC SERVICES CORP ** APA **
Permit Reviews
Permit Number - T18CM04910
Permit Status: Final
Permit Description: COMMERCIAL SOLAR INSTALL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/06/2019 | REVISION - - 1ST | 03/06/2019 | COMPLETED |
| 06/22/2018 | PLANS OK TO SUBMIT - COMM | 06/22/2018 | COMPLETED |
| 06/22/2018 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/09/2018 | COMPLETED |
| 08/08/2018 | RESUBMITTAL | 08/16/2018 | COMPLETED |
| 08/16/2018 | RESUBMITTAL | 03/06/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM04910
Permit Status: Final
Permit Description: COMMERCIAL SOLAR INSTALL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/22/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM04910
Permit Description: COMMERCIAL SOLAR INSTALL
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/04/2019 | ELECTRIC - PROGRESS | DMUNIZ | Approved | CLEAR DGL AFTERHOURS INSPECTION, CHECK #22686 KLS ELECTRIC |
| 03/07/2019 | FRAMING | MHASSAN | Approved | |
| 04/26/2019 | OUTDOOR LIGHTING FINAL | MHASSAN | Approved | |
| 04/26/2019 | ELECTRIC - OUTDOOR LIGHTING | MHASSAN | Approved | |
| 04/26/2019 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | |
| 04/26/2019 | ROOF NAILING | MHASSAN | Approved | |
| 04/29/2019 | ELECTRIC - UFER | MHASSAN | Approved | approved upon 2090 approval |
| 04/29/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | approved upon 1090 approval |
| 04/29/2019 | TEP CLEARANCE - PM | MHASSAN | Approved | CODE DGC |
| 04/29/2019 | ELECTRIC - UNDERGROUND | MHASSAN | Approved | |
| 04/29/2019 | ELECTRIC - FINAL | MHASSAN | Approved | OK to clear solar DGC |
| 04/29/2019 | BUILDING - FINAL | MHASSAN | Approved |