Permit Number: T17CM02103
Parcel: 14027048B

Address:
2825 E GINTER RD

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T17CM02103
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/23/2017 KEN BROUILLETTE FIRE REVIEW Reqs Change Section 1018 of the 2012 IFC requires corridors that have an occupant load of greater than 30 need to be rated. The cover sheet indicates the corridor is not rated. Please clarify
04/20/2017 ERIC NEWCOMB ADA REVIEW Passed
04/24/2017 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. Sheet TS1; Code Study (Area): The drawing indicates an allowable area increase of 100%. Please include the calculation on the drawing, following the IBC Section 506, indicating the allowable increase permitted.
2. Sheet TS1; Code Study (Exits): 6a references Tables 1018.1 and 1004.2.1 for the exit width required. There is no Table 1004.2.1, and Table 1018.1 is for corridor fire resistance rating. Please revise the Table references.
3. Sheet TS1; Code Study (Exits): 6a calculates the required exit width as 82 occupants x .15. Per the IBC Section 1005.3.2, a means of egress capacity factor of 0.2"/occupant should be used for this project. Please verify and revise as required.
4. Sheet TS1; Code Study (Exits): Please finish the line that indicates "82 > 49 so ? exits at 3' required.....".
5. Sheet TS1; Allowable Area Calculation Table: This table indicates no area increase for frontage. Please coordinate with the Code Study.
6. Sheet A1.0; Floor Plan: Please indicate on the drawing the shaded areas on the plan are to be one hour fire resistance rated corridors/rooms with fire partitions per the IBC Section 708 and a one hour fire resistance rated horizontal assembly per the IBC Section 711.
7. Sheet A1.0; Floor Plan: Is the existing stair enclosure (north of the training room 136) constructed per the IBC Section 1009.3.1 to provide the fire resistance rating required? Please indicate on the drawings.
8. Sheet A1.0; Floor Plan: Per the requirements of the IBC Section 1018.4, it appears the corridor 113 exceeds the limit for a dead end corridor. Please verify.
9. Sheet A1.0; Floor Plan/Mezzanine Plan: Do the existing walls and horizontal assemblies in and above the rated areas meet the fire resistance ratings as required by the IBC? Please provide existing partition and horizontal assembly notes and details as required on the drawings.
10. Sheet A1.0; Detail 3: Please provide the connection of the horizontal bracing members to the existing joists. In addition, reference the diagonal bracing size, spacing, and connections to Detail 2.
11. Sheet A1.0; Floor Plan and Mezzanine Plan: Please indicate on the drawings all (new and existing) fire partitions meet the requirements of the IBC Sections 708.4 (Continuity), 708.6 (Openings), 708.7 (Penetrations), 708.8 (Joints), and 708.9 (Ducts and Air Transfer Openings).
12. Sheet A1.0; Floor Plan and Mezzanine Plan: Please indicate on the drawings all (new and existing) horizontal assemblies meet the requirements of the IBC Sections 711.4 (Continuity), 711.5 (Penetrations), 711.6 (Joints), and 711.7 (Ducts and Air Transfer Openings).
13. Sheet A1.0; Floor Plan: Please indicate on the drawings the glazing (existing?) in the conference room 128 and the lobby 100 are rated per the IBC Section 716.6.
14. Sheet A4.0 (Door Schedule); Sheet A1.0 (Floor Plan): Please revise the notes in the Door Schedule for doors 100A, 102, 103, 104, 106, 107, 108, 127, 129, 130, 134, 135, 137, and 139B. These doors should all be rated and include note 3 in the Schedule.
15. Sheet A4.0; Window/Door Schedules: Please indicate on the drawings the purpose of the asterisk on the Window/Door elevations.
16. General: Please provide written responses to all review comments.
04/24/2017 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
04/26/2017 GERRY KOZIOL WWM REVIEW Reqs Change The following is needed for Application Approval:

(Septic - not connected to a Pima County Sewer System)

Need to provide documentation of the existing septic system to pima county building codes (Site@pima.gov).

Need review to verify that the existing septic system size is appropriate for the proposed T.I. as shown on COT building permit #T17CM02103.