Permit Review Detail
Review Status: Completed
Review Details: REVISION - - 2ND
Permit Number - T16CM03514
Review Name: REVISION - - 2ND
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/21/2017 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | The mechanical equipment schedule calls for (3) 250-ton chillers but COMcheck is based on a single 500-ton chiller. (Note: the entering and leaving water temperatures for the chillers and the cooling towers are reversed in the equipment schedules.) [Second comment: The Mechanical Compliance Certificate was not found with this submittal.] [Initial comment: Coordinate the description of the chillers used in the Mechanical Compliance Certificate with the scheduled equipment.] |
| 02/21/2017 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Detail 68/P6.1 still shows shut off valves between the expansion tank and the two water heaters. [Second comment: No shut-off valves are to be located between the expansion tank and the water heaters.] [Initial comment: Revise the water heater detail, 68/P6.1, to relocate the thermal expansion tank to the cold water supply to the water heaters (it is currently shown connected to the natural gas piping). No shut-off valves are to be located between the expansion tank and the water heaters. Provide the size of the thermal expansion tank. Reference: Sections 303.2 and 607.3, IPC 2012.] |
| 02/23/2017 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Approved | |
| 02/23/2017 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 02/27/2017 | KEN BROUILLETTE | FIRE | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 03/06/2017 | LBOJORQ1 | OUT TO CUSTOMER | Completed |