Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T15CM08230
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
02/02/2016 | ROBERT SHERRY | WATER | REVIEW | Completed | |
02/03/2016 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Verify that a cleanout has been provided at the base of each vertical 8" rainwater conductor prior to going underground. Reference: Sections 708.3.4 and 101.8, IPC 2012. |
02/04/2016 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Clarify the installation of the transfer duct and the exhaust duct in the West Main Electrical room (B1-110) with respect to the penetration of fire-rated partitions and the relationship of the ducts with the adjacent structure. Reference: Section 107.2.1, IBC 2012. 2. Coordinate the locations of exhaust fans EF-24 and EF-25 with the mechanical schedule (M702), the electrical power plan, and the type of fan being installed. Reference: Section 107.2.1, IBC 2012. 3. Verify that the UPS room does not require the installation of an exhaust system per Section 502.4, IMC 2012. |
02/19/2016 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. SHEET G003; DEFERRED SUBMITTALS: ARE THERE DEFERRED SUBMITTALS ASSOCIATED WITH THIS PROJECT? IF SO, PLEASE LIST THEM ON THE DRAWINGS. 2. SHEET G010; STAIRWAY REQUIREMENTS: PLEASE CLEAR UP THE VERBIAGE FOR THE LANDINGS. 3. SHEET G010; STAIRWAY REQUIREMENTS: IT IS INDICATED THAT THE EXIT ACCESS STAIRWAY IS NOT REQUIRED TO BE ENCLOSED PER THE IBC SECTION 1009.3. PLEASE INDICATE ON THE DRAWING THE REQUIREMENTS OF 1009.3 EXCEPTION 4 ARE MET (LIST EACH ONE ON THE DRAWING). 4. SHEET G010; PENETRATIONS AT EXIT ENCLOSURE: THIS SECTION REFERENCES THE IBC SECTION 1020.1.2. PLEASE REVISE THE REFERENCE. 5. SHEET G010: WITH THE REMOVAL AND ADDITION OF PLUMBING FIXTURES THROUGHOUT THIS PROJECT, PLEASE INDICATE ON THIS SHEET THAT THE MINIMUM REQUIRED NUMBER OF PLUMBING FIXTURES (WATER CLOSETS, LAVATORIES, SERVICE SINKS, AND DRINKING FOUNTAINS) PER THE IBC TABLE 2902.1 IS MET. 6. SHEET G011; OCCUPANCY PLAN: ARE THE CONCOURSE A AND B INDICATORS REVERSED ON THE PLAN? THE OCCUPANCY LOADS AND DOOR NUMBERS WOULD INDICATE THAT. 7. SHEET G011; OCCUPANCY PLAN: THE TABLE FOR THE TERMINAL EXITING DOES NOT INCLUDE DOOR L1X13 (170 OCCUPANTS). PLEASE VERIFY. 8. SHEETS G011, G012, AND G013: PLEASE DARKEN THE BOXES AND INFORMATION FOR EACH EXIT DOOR NUMBER, CLEAR WIDTH, AND ALLOWED OCCUPANCY LOAD. 9. SHEET G012; OCCUPANCY PLAN: ARE THE CONCOURSE A AND B INDICATORS REVERSED ON THE PLAN? THE OCCUPANCY LOADS AND DOOR NUMBERS WOULD INDICATE THAT. 10. SHEET G012; OCCUPANCY PLAN: THE TABLE FOR THE TERMINAL EXITING DOES NOT INCLUDE DOOR O (170 OCCUPANTS). PLEASE VERIFY. 11. SHEET G017: THE CITY OF TUCSON REQUIRES ALL LETTERING (UPPER AND LOWER CASE) TO BE A MINIMUM OF 3/32" IN HEIGHT. PLEASE REVISE THE RESISTANCE RATINGS AND VARIOUS NOTES. 12. SHEET A001 (LEVEL ONE PLAN); SHEET A626 (ENLARGED PLAN 2): PLEASE INDICATE A NORTH ARROW ON THE ENLARGED PLAN. 13. SHEET A001 (LEVEL 1 PLAN); SHEET A614 (ENLARGED PLAN 7): PLEASE INDICATE A NORTH ARROW ON THE ENLARGED PLAN. 14. SHEET A001 (LEVEL 1 PLAN); SHEET A614 (ENLARGED PLAN 6): PLEASE INDICATE A NORTH ARROW ON THE ENLARGED PLAN. 15. SHEET A002 (LEVEL 2 PLAN); SHEET A610 (ENLARGED PLAN 2): PLEASE INDICATE A NORTH ARROW ON THE ENLARGED PLAN. IT DOES NOT APPEAR TO MATCH THE OVERALL LEVEL 2 PLAN (SHOULD THIS BE 1/A611?). 16. SHEET A002; GENERAL: PLEASE INDICATE A NORTH ARROW ON ALL ENLARGED PLANS REFERENCED ON THIS SHEET. 17. SHEET A002 (LEVEL 2 PLAN); SHEET A611 (ENLARGED PLAN 1): IT DOES NOT APPEAR THE ENLARGED PLAN MATCHES THE OVERALL LEVEL 2 PLAN (SHOULD THIS BE 2/A610?). 18. SHEET A003; TITLE BLOCK: PLEASE REVISE THE KEY PLAN IN THE TITLE BLOCK TO MATCH THE ACTUAL PLAN. 19. SHEET A003; LEVEL 3 PLAN: PLEASE INDICATE THE AREAS ON THIS PLAN SIMILAR TO LEVELS 2 AND 3. 20. SHEET A450; DETAILS 1 AND 2: PLEASE INDICATE ON THE DETAILS THE REQUIRED HEIGHT OF THE HANDRAILS PER THE IBC SECTION 1012. 21. SHEET A501; KEYNOTE LEGEND: NOTE 333 IS INDICATED ON SECTION 2, BUT NOT LISTED IN THE KEYNOTES. PLEASE VERIFY. 22. GENERAL (ARCHITECTURAL): THE GRID LINE NUMBERING AND LETTERING ON ALL PLAN SHEETS DOES NOT MEET THE 3/32" HEIGHT REQUIREMENT. PLEASE REVISE. 23. SHEET S305 (FRAMING PLAN 2); STRUCTURAL CALCULATIONS (SHEET 15): THE CALCULATION INDICATES A MAIN STAIR STRINGER SIZE OF 12 X 3 ½ X 3/8, WHILE THE FRAMING PLAN 2 INDICATES A 12 X 3 X 3/8. PLEASE COORDINATE. 24. GENERAL (STRUCTURAL): PLEASE INDICATE NORTH ARROWS ON ALL ENLARGED STRUCTURAL PLANS. 25. GENERAL: PLEASE PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. |
02/22/2016 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
02/22/2016 | KEN BROUILLETTE | FIRE | REVIEW | Approved | |
02/26/2016 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | TAA PROJECT # 10106674 DWL PROJECT # 1322.00 ACTIVTIE # T15CM08230 Please address the following electrical plan review comments. Also provide a written response. Due to the deficiencies of construction documents for the electrical installations for this project, the electrical plan reviewer was unable to perform a complete electrical plan review. The deficiencies include information required per City of Tucson Commercial Plan Submittal Requirements. These Requirements can be downloaded from www.tucsonaz.gov/pdsd . Example: ELECTRICAL PLAN REQUIREMENTS 1. Electrical floor plan. Assign circuit to each receptacle, light, appliance, meter, disconnect, electrical and mechanical equipment and indicate panel number on all home runs. 2. Complete single line diagrams of service and associated equipment for tenant & building. Voltage and Phase. Panel and Transformer Sizes. Feeder Loads. Including conduit, conductor sizes and types. Ratings of Breakers and Fuses, Including AIC. Complete Fault Current Analysis. Total Building and Service loads. 3. Provide complete panel schedules. 4. 2012 IECC light budget calculations and luminaries switching. 5. Show full compliance with the Tucson Outdoor Lighting Code. Also there where notes that referred to plan sheets that where not included in the plan set. Such as reference to plan sheet E702 and E703, as well as the one line diagrams. Ref: IBC 107.2.1, 2011 NEC. |