Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T15CM04172
Review Name: COMMERCIAL - NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 06/25/2015 | KEN BROUILLETTE | FIRE | REVIEW | Approved | |
| 06/25/2015 | DAVID RIVERA | ZONING | REVIEW | Approved | |
| 07/08/2015 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Completed | |
| 07/08/2015 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Correct the water calculation on sheet P-1 by coordinating the basis for the calculations with the design of the water distribution system (e.g. water meter size). |
| 07/08/2015 | CLAYTON TREVILLYAN | BUILDING-COMMERCIAL | REVIEW | Reqs Change | BUILDING PLAN REVIEW COMMENTS Date: 7-08-15 Activity: T15CM04172, 73, 74 Address: 9013 E. Old Vail Rd. Bldg 1, 2, 3 Applicant: Metro TED This letter reflects comments to be addressed. The purpose of this review is to verify compliance to the 2012 International Building Code and local amendments. In order to facilitate a shorter back check time, we request that you please provide two complete sets of revised plans and calculations, along with a written response to each of the noted items indicating action taken. Other comment references may be derived from additional codes and standards adopted by The City of Tucson. All features have been checked only to the extent allowed by the submittals provided for review. All portions of this project are assumed to meet other departmental requirements, conditions and concerns before permit approval. 1. Provide structural calculations for review, 107.2.1. Sheet SG-1 2. Please reconcile sheet index with the plan pages provided. Ref sheets 1 (site utility), N1, E7, DET11, DET12. Sheet C1 3. Please reconcile sheet index with the plan pages provided. Ref sheets 1 (site utility), N1, E7, DET11, DET12. Sheet A-2 4. Clarify the hardware sets for doors #5 and 7. Information is not consistent with door selection. 5. Specify doors #9 and 10. No door information is provided. Sheet E2 6. Revise sheet for proposed door and window layout consistent with other plan pages. If you have any questions please contact: Clayton Trevillyan, CBO 520.837.4913 Clayton.Trevillyan@tucsonaz.gov |
| 07/08/2015 | ROBERT SHERRY | WATER | REVIEW | Reqs Change | The maximum demand allowed by Tucson Water for a 1" water meter is 37.5 GPM, not 39.2 GPM; correct the water calculation on sheet P-1. |
| 07/13/2015 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please provide the following documents or information. #1. Please verify or indicate on the electrical plans that the electrical service and associated equipment downstream, shown on plan sheet E1 is typical for each building and suite, and is to be labeled or identified as to the loads served. #2. Please correct the feeders indicated on the riser diagram for the panels to, 4-#3/0 cu + 1-#6 cu gnd. This is to accommodate the three phase panel requirements. ( 3 ungrounded , 1 grounded, and 1 equipment gnd ). #3. Please provide complete tenant and building load calc's. #4. Please indicate feeder conductor sizes and types for the feed to the building service equipment from the utility. #5. Please provide luminaire switching requirements for code compliance with the IECC as per sec.C405.2.2.1, C405.2.2.2 #6. Lamp color temperature output not to exceed 3500K for exterior lighting per sec.402.1, Tucson Outdoor Lighting Code. Ref; IBC sec.107.2.1, NEC art. 110, 300, 408.4. |
| 07/16/2015 | ELIZABETH LEIBOLD | ENGINEERING | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 08/18/2015 | AROMERO4 | OUT TO CUSTOMER | Completed |