08/21/2014 | JASON GREEN | ENGINEERING | REVIEW | Reqs Change | Building Plan can not be approved until approval of the DP Package DP14-0086. Building plan will be approved upon approval of the DP. JG |
08/26/2014 | KEN BROUILLETTE | FIRE | REVIEW | Approved | |
08/27/2014 | STEVE SHIELDS | ZONING | REVIEW | Denied | PDSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: Truly Nolen T14CM04154 Building Plan (2nd Review) TRANSMITTAL DATE: August 27, 2014 1. The building plans have been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. Zoning has reviewed the building plans but cannot approve until a development package has been approved. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved development package. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 |
09/04/2014 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Approved | |
09/05/2014 | ROBERT SHERRY | WATER | REVIEW | Completed | |
09/05/2014 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | Coordinate the building design with the component descriptions shown in Section 3 of the Envelope Compliance Certificate (e.g. the roof has R19 cavity insulation, not R-38 cavity insulation. Provide the NFRC certification data for the skylights, windows, and glass doors (see footnote (c) on Section 3 of the Envelope Compliance Certificate. [Initial comment: Provide energy code compliance calculations for the building envelope; use the climate zone for Tucson. Provide sufficient detail on the drawings to evaluate the energy compliance of the building envelope. The information shall, as a minimum, include U-factors of the envelope systems and fenestration components, along with the R-values of the insulation and the SHGC for the fenestration. Reference: Sections C103.2 and C401.2, International Energy Conservation Code 2012.] |
09/05/2014 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Verify the flow direction for sanitary sewer branch 8578-01. According to GIS map data, the branch flows north to manhole 8578-02. If true, then manhole 8578-01, with a rim elevation of approximately 2572 feet, is the upstream manhole, not 8578-02. [Initial comment: Provide the rim elevation of the next upstream sanitary manhole cover. Determine the need for a backwater valve per Section 715.1, IPC 2012, as amended by the City of Tucson.] |