Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T14CM01299
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/20/2014 | MARTIN BROWN | FIRE | REVIEW | Denied | Please define hanger cllassification per NFPA 409. All requirements for hanger classification must be maintained for the life of the building. Also, please provide sprinkler design criteria (per NFPA 13 and NFPA 409), including current flow data, on the plans. |
05/22/2014 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Reqs Change | sheet 2.1.1 1. Detail 1: a. Provide a handrail on the west side of the ramp. b. Provide a 5'-0" long concrete landing at the bottom of the ramp. c. Provide a removable gard rail at the painted step edge nosing d. All gardrails are to be 42" high as per 2012 IBC, Section 1012. e. all handrails are to be between 34" and 38" high. SHEET 6.3.1 2. Details 6a and 6b: a. Reference comments 1a through 1e above. b. Show dimensional sizes of all risers. c. Provide a elevation of the ramp handrail d. All guards are to comply with 2012 IBC, section 1013. e. All handrails are to comply with 2012 IBC, Section 1012 and the 2009 ICC A117.1, Sections 405.8 and 505. END OF REVIEW |
05/22/2014 | RONALD BROWN | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | |
05/23/2014 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Clarify the termination of the pumped drain from the evaporative cooler. The plumbing vents may only be used for venting of the plumbing system. Reference: Section 901.3, IPC 2012. 2. Provide drainage calculations for the shed roof along with dimensions for the gutter and downspouts. Reference: Sections 1101 and 1106.6, IPC 2012. |
05/23/2014 | ROBERT SHERRY | WATER | REVIEW | Approved | |
05/23/2014 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Demonstrate energy code compliance for the addition to the building envelope. Reference: Sections C101.4.3, C101.5, and C103.2, International Energy Conservation Code 2012. 2. Provide heating load calculations that justify the capacities of the heating equipment specified for the project. Reference: Sections C403.2.1 and C403.2.2, IECC 2012. 3. Provide calculations demonstrating adequate ventilation and exhaust flow rates for the occupancy-type (e.g. education, wood/metal shop per Table 403.3, IMC 2012) of the addition. Reference: Section 403.2, IMC 2012. |
06/02/2014 | LEERAY HANLY | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Plan review has been completed and the following corrections are required. Please provide a written response to comments with plan re-submittal. 1) The City of Tucson Outdoor Lighting code limits all outdoor lighting to a maximum color temperature of 3500K. Noted "L3" fixtures exceed this. Reference section 402.1 of Outdoor Lighting Code. 2) Noted "L2" fixtures are not full cut-off fixture and are therefore subject to the lumen cap requirements of Table 401.1 and the plan submittal requirements of section 102.4.2 of the OLC which means a complete lighting inventory for the site. Please note that if these fixtures were full cut-off luminaires then they would not be counted per 401.2.1(3) of OLC. If there are questions regarding this review contact: LeeRay 520-837-4906 LeeRay.Hanly@tucsonaz.gov |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
06/09/2014 | SHANAE POWELL | OUT TO CUSTOMER | Completed |
06/09/2014 | CPIERCE1 | REJECT SHELF | Completed |