Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
7211 S PARK AV
Address NEW:
7211 S PARK AV
Apply Date:
03/05/2014
Applicant:
N/A
Description:
COMMUNITY COLLEGE
Contractors:
  • BOWEN CONSTRUCTION L L C

Permit Reviews

Permit Number - T14CM01299
Permit Status: C of o
Permit Description: COMMUNITY COLLEGE
Start Date Submittal Complete Date Status  
03/05/2014 PLANS OK TO SUBMIT - COMM 03/05/2014 COMPLETED Review Details
05/15/2014 COMMERCIAL - TI 06/09/2014 COMPLETED Review Details
06/25/2014 RESUBMITTAL 07/10/2014 COMPLETED Review Details
07/10/2014 RESUBMITTAL 12/09/2014 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T14CM01299
Permit Status: C of o
Permit Description: COMMUNITY COLLEGE
Total Outstanding Activity Conditions - 1
Date Name
03/05/2014 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T14CM01299
Permit Description: COMMUNITY COLLEGE
Total Completed Inspections - 31
Date Description Inspector Results Comments
08/18/2015 SHEET ROCK NAILING MRAMBER Approved IVRS - Inspection :*
09/21/2015 FIRE SPKLR - FINAL CSCHULTZ Approved
10/06/2015 FIRE - ALARM FINAL CSCHULTZ Approved
10/08/2015 PLUMBING - GAS PRESSURE TEST MRAMBER Approved IVRS - Inspection :*
10/13/2015 ELECTRIC - ABOVE CEILING MRAMBER Approved PER BU FINAL
10/13/2015 ELECTRIC - TEMP POWER FOR TEST MRAMBER Approved PER BU FINAL
10/13/2015 ELECTRIC - PROGRESS MRAMBER Approved PER BU FINAL
10/13/2015 ELECTRIC - OUTDOOR LIGHTING MRAMBER Approved PER BU FINAL
10/13/2015 MECHANICAL - INTERMEDIATE MRAMBER Approved PER FINAL
10/13/2015 PLUMBING - ROOF DRAINS MRAMBER Approved
10/13/2015 REINFORCED MASONRY PRE-GROUT MRAMBER Approved
10/13/2015 EXT METAL CLIPS/EXT SHEATHING MRAMBER Approved
10/13/2015 ROOF NAILING MRAMBER Approved
10/13/2015 BUILDING ABOVE CEILING MRAMBER Approved
10/13/2015 STUCCO MESH MRAMBER Approved
10/13/2015 U VALUE FOR WINDOW MRAMBER Approved PER BU FINAL
10/13/2015 MECHANICAL - FINAL MRAMBER Approved IVRS - Inspection :*
10/13/2015 PLUMBING - FINAL MRAMBER Approved IVRS - Inspection :*
10/13/2015 ELECTRIC - FINAL MRAMBER Approved IVRS - Inspection :*
10/13/2015 BUILDING - FINAL MRAMBER Approved IVRS - Inspection :*
10/13/2015 STEM WALL/RETAINING WALL MRAMBER Approved IVRS - Inspection :*
10/13/2015 BUILDING PRE-SLAB MRAMBER Approved IVRS - Inspection :*
10/13/2015 ELECTRIC - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
10/13/2015 BUILDING - PROGRESS MRAMBER Approved IVRS - Inspection :*
10/13/2015 FRAMING MRAMBER Approved IVRS - Inspection :*
10/13/2015 EXCAVATION/LAYOUT REBAR & ZON MRAMBER Approved IVRS - Inspection :*
10/13/2015 MECHANICAL - FINAL MRAMBER Approved IVRS - Inspection :*
10/13/2015 PLUMBING - FINAL MRAMBER Approved IVRS - Inspection :*
10/13/2015 ELECTRIC - FINAL MRAMBER Approved IVRS - Inspection :*
10/13/2015 BUILDING - FINAL MRAMBER Approved IVRS - Inspection :*
10/15/2015 FIRE - FINAL kenb Approved