Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T13CM04749
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/06/2013 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Provide information to show that the installation of the thermal expansion tank for the water heater (detail 15/M6.1) complies with the manufacturer's listing requirements (i.e. on the cold water supply line, between the water heater and the backflow preventer or other one-way device). Reference: Sections 303.2 and 607.3.2, IPC 2012. 2. Provide a full-open valve for the water supply pipe to the water heater. Reference: Section 606.1(8), IPC 2012. |
08/06/2013 | ROBERT SHERRY | WATER | REVIEW | Approved | |
08/06/2013 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Revise the mechanical design as required to avoid using the corridor as a return air duct. Reference: Section 601.2, IMC 2012. 2. Smoke detectors shall be located upstream of any outside air connections (AC-1). Reference: Section 606.2.1, IMC 2012. |
08/09/2013 | MARTIN BROWN | FIRE | REVIEW | Approved | |
08/15/2013 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | SHEET CVR 1. The Project Location aerial plan does not depict the actual configuration of the project. Please revise and resubmit. SHEET AD1.1 2. Please identify any and all rated partitions. a. Show original rated separation of building as indicated in Project Description on CVR Sheet and the effect that this project configuration has on required separations and show possible adjustments as required by code to maintain those separations. SHEET A1.1 3. Please verify that the demising partition next to rooms 102, 106, 108, 110 and 111 is in fact a concrete partition as noted. 4. Please identify all new partitions with a different delineation from the existing partitions. a. Insure all new partitions have a partition type reference. 5. Identify the other concrete partition with note 1. a. Are these partitions rated separation partitions? SHEET A3.1 6. At note 8, reference detail 3/A5.1 for bracing. SHEET A4.1 7. At details 4, 5 and 6, show the sink 2'-10" above finished floor as required by 2009 ICC A117.1, Section 606.3. 8. At details 1 and 3, show the vertical grab bar as required by 2009 ICC A117.1, Section 604.5.1. 9. Note 15 references the water dispenser to the mechanical drawings. The mechanical drawings do not show the water dispenser. Please reconcile. SHEET MA.1 10. Please provide structural calculations and structural details for all new roof top mounted and/or suspended HVAC equipment. END OF REVIEW |
08/19/2013 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | T13CM04749 3820 E Hemisphere LP #146 TI 1. Sheet E1.0, circuits and Panel designations are required to be assigned even where existing circuits are to be reused rather than to indicate use existing circuits. Ray T Majuta Elect Plan Review PDSD, Tucson 8/19/2013 Ray.Majuta@tucsonaz.gov |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
08/26/2013 | CPIERCE1 | REJECT SHELF | Completed |