Permit: T13CM04749
Permit Details
Status:
L of c
Type:
COMMERCIAL ALTERATION
Address:
3280 E HEMISPHERE LP #146
Address NEW:
3280 E HEMISPHERE LP #146
Apply Date:
08/02/2013
Applicant:
ADVANTECH FACILITY DESIGN
Description:
TI: OFFICE
Architects:
- IAN RECAN
Contractors:
- KACHINA CUSTOM HOMES II INC
Outstanding Activity Conditions
Permit Number - T13CM04749
Permit Status: L of c
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/02/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T13CM04749
Permit Description: TI: OFFICE
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/16/2013 | PLUMBING - PRE SLAB | MRAMBER | Approved | 1. SHOWER AREA - WALLS OK TO COVER 2. RMS 112 - 117 OK TO ROCK 3. RMS 125 & 126 OK TO ROCK |
| 09/16/2013 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 09/16/2013 | PLUMBING - PRE SLAB | MRAMBER | Approved | IVRS - Inspection :* |
| 09/17/2013 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | IVRS - Inspection :* |
| 10/14/2013 | PLUMBING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 10/14/2013 | PLUMBING - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/29/2013 | BUILDING - FINAL | MRAMBER | Approved | OK TO OCCUPY AREA DESIGNATED AT PHASE 1. T.F.D. HAS APPROVED ALL E. LIGHTING AND EXITS THIS AREA. NO LIFE SAFETY ISSUES OBSERVED. |
| 10/29/2013 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 10/29/2013 | PLUMBING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 10/29/2013 | ELECTRIC - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 10/29/2013 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 10/29/2013 | FIRE - FINAL | wmotto | Approved | 1. ok to occupy phase E. per tucson fire |
| 10/29/2013 | FIRE SPKLR - FINAL | wmotto | Approved | |
| 11/25/2013 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | STORAGE & QC ROOM ELEC INT OK |
| 11/25/2013 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 11/25/2013 | FRAMING | MRAMBER | Approved | IVRS - Inspection :* |
| 11/29/2013 | SHEET ROCK NAILING | IVR USER | Approved | IVRS - RI canceled |
| 12/27/2013 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 12/27/2013 | ELECTRIC - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 12/27/2013 | BUILDING ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 01/28/2014 | BUILDING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 01/29/2014 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
| 01/29/2014 | NPPO - FINAL | RLEDONNE | Approved | |
| 01/29/2014 | SIGN - FINAL | RLEDONNE | Approved | |
| 01/29/2014 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 01/29/2014 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 01/30/2014 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | PER MECH FINAL - MRAMBER |