Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T12CM08253
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
03/06/2013 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | 1. Somewhere in the plumbing drawings, details and statements needs to be included to clarify that the water heater is wall mounted and refered to the structural drawings for details and calculations. Detail 2/P1.2 seems to be the most logical place for this requirement however it is clearly showing a floor mounted system. Please modify detail 2/P1.2 to diagramaticly show a wall mounted water heater and refer to the structural details. END OF REVIEW |
03/15/2013 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. A revised sheet P1.0 has not been submitted. [Original comment: Complete detail 2/P1.0 to show the pipe sizes and the flow rate for the recirculation system (all currently shown as "X"). Reference: Section 103.2.3, UPC 2006.] 2. Comment not resolved; the architect shall provide sufficient details to demonstrate compliance to Sections 401.1, 406.0, and 411.0, UPC 2006. [Original comment: Clarify the nature of the proposed mop sink. The architectural and plumbing drawings indicate that the mop sink is to be constructed on site but the preliminary kitchen drawings indicate that the general/plumbing contractor will supply the sink. Provide construction details if the sink is to be constructed on site. Reference: Sections 401.1, 406.0, and 411.0, UPC 2006.] 3. Comment not resolved; absent a structural issue, each vent pipe shall rise vertically to a minimum of 6" above the flood-level rim of the fixture it serves before offsetting horizontally (see P-1 in rooms 101, 105, and 109). [Original comment: Each vent pipe shall rise vertically to a minimum of 6" above the flood-level rim of the fixture it serves before offsetting horizontally. Reference: Section 905.3, UPC 2006.] |
03/15/2013 | ROBERT SHERRY | WATER | REVIEW | Approved | |
03/18/2013 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Comment not resolved; the 16"x 13", 16"x 30", and the 24"x 22" ducts have velocities less than 1500 FPM. [Original comment: Revise the size of the grease ducts to provide a minimum velocity of 1500 feet per minute at full flow conditions. Reference: Section 506.3.4, IMC 2006, as amended by the City of Tucson.] 2. The submitted shop drawings show a zero-clearance Type I hood but nothing in the specifications includes this requirement. [Original comment: Verify that the hood installation complies with Section 507.9, IMC 2006 for clearances. Wall type L allows both metal and wood studs and the J (stainless steel panels) and K (tile) notations for the wall covering do not indicate the extent of either wall covering (also, the kitchen drawings are marked "Preliminary - not for construction").] |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
03/27/2013 | SHANAE POWELL | OUT TO CUSTOMER | Completed |
03/27/2013 | CPIERCE1 | REJECT SHELF | Completed |