Permit Number: T12CM08030
Parcel: 11706117B

Address:
504 E 9TH ST

Review Status: Completed

Review Details: COMMERCIAL - NEW

Permit Number - T12CM08030
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
05/08/2013 STEVE SHIELDS ZONING REVIEW Denied PDSD TRANSMITTAL

FROM: Steve Shields
Lead Planner

PROJECT: The Junction At Iron Horse
T12CM08030
Building Plan (2nd Review)

TRANSMITTAL DATE: May 8, 2013

1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed.

2. Zoning can not approve the building plan until a development package has been approved.

3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved development package. Additional comments may be forthcoming.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956
05/15/2013 LOREN MAKUS ENGINEERING REVIEW Denied The Development Plan must be approved before the building plans are approved.
05/16/2013 KEN BROUILLETTE FIRE REVIEW Denied 1. Please add notes that building is required to have Standpipes.
2. Please note that all Shafts (stairways) are rated and change plans indicating that change.
3. Add note on front page that Fire Alarm Permit is deferred.
4. Please indicate that S-2 occupancy sprinkler system design will be NFPA 13 not NFPA 13R which is for the remainder of the Group R occupancy.
05/16/2013 LEERAY HANLY PLUMBING-COMMERCIAL REVIEW Reqs Change P1.2
Riser reference to 1/p4.8 near gridline 13.2 is incorrect I think you mean 3/P4.3.

P1.3
Riser reference near gridline 6 is reference to 1/P4.8 is incorrect. 3/P4.3 & 1/p4.6 appear to be correct risers.
Riser reference near gridline 10.8 to 4/P4.2 should be 4/P4.8

P1.4
Near gridline V.3 is reference to 1/P4.9 -- should be 1/P4.5
Riser stack on 1/P4.5 is missing outdoor shower P7A.

P2
Detail reference for booster pump should be 5/P5.1
05/16/2013 LEERAY HANLY ELECTRICAL-COMMERCIAL REVIEW Approved
05/16/2013 LHANLY1 WATER REVIEW Approved
05/16/2013 LEERAY HANLY BUILDING-COMMERCIAL REVIEW Reqs Change There are no plans for a firepump room. Please clarify if one will be needed. Fire pump may be part of deferred submittal for sprinkler system, but electrical, plumbing, and fire ratings of walls need to be considered.

PP A0.2
Errata, occupant load building 1 at 4th floor incorrect.
Errata, applicable Fire code should be noted as 2006 IFC
Please provide copy of appeal or appeal # noted for Area of refuge modification to code.

PP A1.0
Pool area has an occupant load over 50. Provide two exits with gates swinging in direction of egress.
Details 6,7,10 for ramps do not show edge protection per ANSI 405.9.

PP A2.0A
Detail references have not been filled out and either several keynote references are placed in wrong area or there is a missing overlay (eg notes 2,5 gridline y)

PP A2.1A
Cut details notes not filled out

PP A3.0
Detail 7 - there are no 5a & 5b details on A6.3

PP A4.6
Keynotes don't jibe with sections.

PP A7.0
Keynote 7 calls for a rated door while labels say non-rated; clarify
For an non-rated exterior stair shaft you need one "open" side with a minimum of 35 square feet of aggregate open area at each floor and landing level. IBC 1023.3

PP A7.1
Clarify if this is an interior or exterior starirway. An interior stair shaft must be rated, and exterior stair requires one open side.

PP A7.2 & A7.3 similar
Non rated exterior stairs require one "open" side with a minimum of 35 square feet of aggregate open area at each floor and landing level. IBC 1023.3

PP A7.4
Elevator section has incorrect detail references.
05/16/2013 LEERAY HANLY MECHANICAL-COMMERCIAL REVIEW Reqs Change Mechanical unit plans have incorrectly noted scale to the drawings (which is of course better than having 120' dryer ducts)

PP M1.4
Community rooms and Amenity areas ot meet IMC 403.2.1(4). Provide sequence of operation for FC 5,6,8 to address recirculation of air from restroom.
05/16/2013 LHANLY1 COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
05/24/2013 CPIERCE1 REJECT SHELF Completed