Permit Number: T11CM03210
Parcel: 13824101K

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T11CM03210
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
12/02/2011 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied Comment not resolved; details A/CA-4 and C/CA-4 clearly show that the primary storm drainage from the canopy is by way of 3" rain leaders connecting to the perimeter gutter of the canopy. The secondary storm drainage for the canopy is from scuppers cut into the side of the perimeter gutter. In detail C/CA-4, the rain leader is shown with two options: terminate at the face of the pump island, or connect directly to an underground storm drain system. Provide a cleanout at the base of each leader, prior to the connection to the horizontal drain if the leaders do not terminate at the face of the pump island. (In addition, the minimum height of a scupper is 4", not 2" as shown in detail G/CA-4.1. Detail A/CA-4 shows that the height of the gutter is 8" so increasing the height of the scuppers should not be a problem. Reference: Section 1101.11.2.1, UPC 2006. [Original comment: If the 3" PVC rain leaders terminate directly to an underground storm drainage system, provide a cleanout at the base of each leader, prior to the connection to the horizontal drain. Reference: Section 1101.12.1, UPC 2006.]
12/07/2011 RONALD BROWN BUILDING-COMMERCIAL REVIEW Approved
12/09/2011 DAVID RIVERA ZONING REVIEW Denied The Development Plan is still under review through the CDRC Review Process. As of this review date 12/9/11, the development plan has not been approved. Zoning will re-review the Canopy Plans on the next submittal and compare them to the approved development plan. Zoning will review the Canopy building plans to ensure compliance with the approved development plan if the DP has been approved and stamped by the CDRC manager. If available include a copy of the approved DP on the building submittal. Additional comments may be forthcoming.
12/29/2011 LEERAY HANLY ELECTRICAL-COMMERCIAL REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
01/04/2012 FERNE RODRIGUEZ REJECT SHELF Completed
01/03/2012 CPIERCE1 OUT TO CUSTOMER Completed