Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL NEW
Permit Number - T10CM02212
Review Name: COMMERCIAL NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/11/2010 | SREEVES1 | ADA | REVIEW | Passed | |
| 08/12/2010 | MARTIN BROWN | FIRE | REVIEW | Denied | Fire Comments: The exit corridor needs fire rating. See IFC 1017. this includes doors, walls, etc. A separate submittal is required for the fuel tanks. Three sets of permit drawings and two sets of fuel tank, piping and dispenser cut sheets need to be submitted. |
| 08/18/2010 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | |
| 08/18/2010 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | 1. Please provide a Deferred Submittal Letter listing all the items being deferred to Leeray Hanly for additional fee accessment. 2. Lettering style on several sheets is below our 3/32" minimum policy. Please change all sheets accordingly and resubmit. 3. Please provide structural calculations for Light Pole foundations. 4. Please provide structural wall support detail for the water heater and structural calculations. 5. Please provide load calculations for all roof top mounted HVAC equipment. 6. Need Health Department review. 7. Please review the list of special inspections assigned in the Conditions Sections. Please verify these requirements and provide completed Special Inspection Certifications for review and approval. SHEET A1.2 6. Please provide a 1 hour fire rated exit corridor out the West side. END OF REVIEW |
| 08/18/2010 | RONALD BROWN | HC | REVIEW | Approved | |
| 08/24/2010 | TERRY STEVENS | ZONING | REVIEW | Denied | 08/24/2010 Development Services Department Zoning Review Section Terry Stevens Lead Planner Comments: 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site plan. Additional comments may be forthcoming. |
| 08/25/2010 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Provide a design for the mounting shelf for the water heater along with structural calculations to show that the water heater is safely supported. Reference: Sections 310.0 and 314.5, UPC 2006. 2. Show that the floor of the restroom slopes toward the floor drain. Reference: Section 411.2, UPC 2006. 3. The branch piping size called out for the urinal flush valve will result in a water velocity greater than 8 FPS. Limit the water velocity to less than 8 FPS for the copper piping. Reference: Sections 610.12 and A 6.1, UPC 2006 and IS 3-2003, Section 2.6. 4. Provide a floor drain adjacent to the 3-compartment sink per Section 704.3, UPC 2006. 5. The 2-way cleanout shown in Detail 6/P1.3 is in violation of Section 707.6, UPC 2006. Section 707.4 (4), UPC 2006 allows the use of an approved, 2-way cleanout fitting (note that "fitting" is singular) only as a substitute for an upper terminal cleanout. 6. Provide cleanouts sized per Section 707.11, UPC 2006. 7. Provide a cleanout at the base of each roof drain leader prior to its connection with the horizontal storm drain. Reference: Section 1101.12.2, UPC 2006. |
| 08/26/2010 | ROBERT SHERRY | WATER | REVIEW | Denied | Tucson Water limits a 1-1/2" meter to a maximum demand of 50 GPM. Provide a letter from Tucson Water confirming that the use of a 1-1/2" water meter will be allowed for this project (59 GPM). Reference: Sections 610.2 and 610.12, UPC 2006. |
| 08/26/2010 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. This project is under the jurisdiction of the City of Tucson, not Marana (Sheet M1.2, Condensate drains). 2. Provide energy code compliance calculations using the correct climate zone (Pima County < 4,000 feet, not the town of Pima, Arizona). Revise the calculations to match the construction of the building (e.g. the walls and the roof). Reference: Sections 101.4 and 104.2, International Energy Conservation Code 2006. 3. Specify the minimum resistance (R-value) of the duct insulation to be used on this project. Reference: Section 503.2.7, IECC 2006, as amended by the City of Tucson. 4. Revise the ventilation calculations to coordinate with this activity (i.e. this is not an "education and office classification" and there is not a 2275-square foot office). Reference: Section 401.2, IMC 2006. 5. Clarify the amount of outside air to be supplied by each roof-top unit; the equipment schedule refers to the calculations which are ambiguous and the air balance schedule has different outside air quantities. Reference: Section 106.3.1, IMC 2006. 6. Revise the sequence of operation for the restroom exhaust fans so that all of the air supplied to the restrooms will be exhausted. Reference: Section 403.2.1 (4), IMC 2006. 7. Show the location of keynote 6 on sheet M1.1.1 (EF-B1?). Reference: Section 106.3.1, IMC 2006. |
| 08/31/2010 | BIANCA RAMIREZ | ENGINEERING | REVIEW | Denied | Building plans cannot be approved until the site plan has been approved. |
| 09/10/2010 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | Project: T10CM02212 New Circle K 1025 E Park Electrical Plans denied for following: 1. Must first obtain Deferred Submittal on Fire Alarm System for Building Official. 2. As per Commercial Submittal Requirements, plans must be minimum text size of at least 3/32'', all notes, information of any type, etc. 3. Sheet E6.0, indicate size of conductors between Utility and 800 amp Main Section, in this Jurisdiction customer installs, Utility terminates. 4.Cannot locate circuits D 9 and 11 on power plan. 5. Indicate circuits B 20 and 22 on power plan. Ray T Majuta Elect Plan Ck PDSD, City of Tucson, 9/13/10 Ray.Majuta@tucsonaz.gov |
| 09/14/2010 | GERRY KOZIOL | WWM | REVIEW | Denied | NEEDS WASTE WATER CREDIT EVALUATION- 5TH FLOOR 740-6602 NEED CAPCITY EVALUATION- 3RD FLOOR- KURT STEMM-740-7702 NEED A COPY OF SEWER CONNECTION FOR BASSE MAP UPDATE |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 10/01/2010 | GERARDO BONILLA | OUT TO CUSTOMER | Completed |
| 10/01/2010 | SUE REEVES | REJECT SHELF | Completed |